DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 37 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:37 awarded · Kandy
0%

0

Delay

0 / 37 awarded

Portfolio Breakdown · Kandy · District

579Awarded739Total
Kandy 37 awarded of 42 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn87188%706.5515.0512.057.811% of contract99.5%35.0%
Tender Below 50Mn2420483%716.0454.4332.1162.036% of contract80.0%78.1%
DL Stage 01440100%110.3110.3110.389.381% of contract100.0%100.0%
DL Stage 02440100%140.3140.3140.386.962% of contract100.0%100.0%
DL Stage 03220100%24.324.324.318.074% of contract100.0%100.0%
DL Stage 040000%0.00.0————
PIU0000%0.00.0————
Not Specified0000%0.00.0————
Kandy4237588%1,697.41,244.41,119.1414.133% of contract89.1%75.9%

Avg Physical Progress per EE Division · Kandy

Portfolio Timeline· 37 scheduled projects · Kandy Toggle
Portfolio · Awarded Works

Awarded Projects

13 projects

13/13 (filtered)

Filter awarded works

13 matching projects1 active

ActiveCritical Delay
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/04/25/13/CP/KYRR/RDA/04/25/13
Gonaala Pasala Asala Sita Kubukkadura Athuru Margayak Wana Gurumada Margaya
37%
35,195,820.0042,644,514.03Awarded
2RR/RDA/04/25/19/CP/KYRR/RDA/04/25/19
Mulgama viduhala Asala sita lewalan dakwa
35%
25,917,512.5046,131,296.30Awarded
3RR/RDA/04/25/20/CP/KYRR/RDA/04/25/20
Carpeting road Ratemulla to Wendesiwaththa End
45%
36,995,817.1040,119,276.86Awarded
4RR/RDA/04/25/21/CP/KYRR/RDA/04/25/21
Galaha group sita finas kotasa Pahalagama-Ihalagama haraha nawa rohala dakwa Margaya
80%
22,711,029.0040,719,533.36Awarded
5RR/RDA/04/25/24/CP/KYRR/RDA/04/25/24
Galamuduna gamata pivisena Margaya
0%
157,638,978.90201,921,834.86Awarded
6RR/RDA/04/25/25/CP/KYRR/RDA/04/25/25
Delgasthenna Road
0%
56,035,922.2478,736,509.47Awarded
7RR/RDA/04/25/28/CP/KYRR/RDA/04/25/28
Dehideniya sita Hedeniya dakwa Margaya
35%
38,495,776.0041,827,394.04Awarded
8RR/RDA/04/25/31(1)/CP/KYRR/RDA/04/25/31(1)
Paththunupitiya School road to Gampola Road through Pallegama Anguruwala
30%
50,476,865.2865,989,182.36Awarded
9RR/RDA/04/25/41/CP/KYRR/RDA/04/25/41
Karyala handiya pahala margya concrete kirima
85%
22,047,564.0039,022,781.94Awarded
10RR/RDA/04/25/52/CP/KYRR/RDA/04/25/52
Bokalawela Road from Hapugoda Junction to Ranawana (Drinage System Development and Road)
60%
50,478,905.0072,631,674.77Awarded
11RR/RDA/04/25/54
Development of the Dolapihilla road from Navinnapitiya via Deldeniya
20%
65,808,186.5073,819,405.52Awarded
12RR/RDA/04/25/55
Development of entrance roads, pedestrian rest areas and parking areas of the Sri Dalada Maligawa premises
40%
83,080,000.0098,049,399.56Awarded
13RR/RDA/04/25/56
Renovation of road Haidri estate to Barcapal
25%
51,476,130.0056,051,060.70Awarded
Showing 1–13 of 13
Per page:
Source: DRRRP • 42 projects • Data updated 2026-11-02 10:30 • 14:23:24