DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 15 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-02 10:30Live
Graphs reflect current view:15 awarded · EE: Puttalam
75% awarded
0
Awarded
20 total projects 20 roads in portfolio
Awarded projects15
RR/RDA/19/25/01/NWP/PUTDevelopment of carpeting the Gammedda road up to Anathapara.RR/RDA/19/25/05/NWP/PUTDevelopment of the road from near Mr. Chaminda's house to Boga PathahaRR/RDA/19/25/08/NWP/PUTCarpeting of Velasia Main Road from Madurankuliya.RR/RDA/19/25/26/NWP/PUTAbayarama Mawatha Bomimakka Kovil Road to Sembandaluwa Temple RoadRR/RDA/19/25/28/NWP/PUTSamagi MawathaRR/RDA/19/25/29/NWP/PUTDevelopment of the road from Galkuliya Welameda to Mrs. Deepani's houseRR/RDA/19/25/30/NWP/PUTDevelopment of carpeting from Mihirajthotupola to Serakkuliya 1 on the Serakkuliya main roadRR/RDA/19/25/31/NWP/PUTDevelopment of carpeting from the point where carpeting has stopped on the Tammana main roadRR/RDA/19/25/32/NWP/PUTDevelopment of the Bammeyaya RoadRR/RDA/19/25/33/NWP/PUTDevelopment of the road from near the Sugatarama Temple, Periyakulam to ThalgaswewaRR/RDA/19/25/34/NWP/PUTCarpeting & Development of Bodhirajapura 4th LaneRR/RDA/19/25/03Nawagattegama Rohala Pare sita Thapal Karyalaya Dakwa margaya (Nawagattegama)RR/RDA/19/25/02Concrete development of the road from Hopper Kada junction to Elu Farm.RR/RDA/19/25/35Carpeting & Development of Kolithatissa Mawatha
+1 more…
Click to filter the awarded table
399.5M
399.5 Mn
Contract Value
Awarded projects15
RR/RDA/19/25/01/NWP/PUTDevelopment of carpeting the Gammedda road up to Anathapara.RR/RDA/19/25/05/NWP/PUTDevelopment of the road from near Mr. Chaminda's house to Boga PathahaRR/RDA/19/25/08/NWP/PUTCarpeting of Velasia Main Road from Madurankuliya.RR/RDA/19/25/26/NWP/PUTAbayarama Mawatha Bomimakka Kovil Road to Sembandaluwa Temple RoadRR/RDA/19/25/28/NWP/PUTSamagi MawathaRR/RDA/19/25/29/NWP/PUTDevelopment of the road from Galkuliya Welameda to Mrs. Deepani's houseRR/RDA/19/25/30/NWP/PUTDevelopment of carpeting from Mihirajthotupola to Serakkuliya 1 on the Serakkuliya main roadRR/RDA/19/25/31/NWP/PUTDevelopment of carpeting from the point where carpeting has stopped on the Tammana main roadRR/RDA/19/25/32/NWP/PUTDevelopment of the Bammeyaya RoadRR/RDA/19/25/33/NWP/PUTDevelopment of the road from near the Sugatarama Temple, Periyakulam to ThalgaswewaRR/RDA/19/25/34/NWP/PUTCarpeting & Development of Bodhirajapura 4th LaneRR/RDA/19/25/03Nawagattegama Rohala Pare sita Thapal Karyalaya Dakwa margaya (Nawagattegama)RR/RDA/19/25/02Concrete development of the road from Hopper Kada junction to Elu Farm.RR/RDA/19/25/35Carpeting & Development of Kolithatissa Mawatha
+1 more…
Click to filter the awarded table
Avg
74.3%
9
works in progress
6 completed
Avg Progress
Awarded projects15
RR/RDA/19/25/01/NWP/PUTDevelopment of carpeting the Gammedda road up to Anathapara.RR/RDA/19/25/05/NWP/PUTDevelopment of the road from near Mr. Chaminda's house to Boga PathahaRR/RDA/19/25/08/NWP/PUTCarpeting of Velasia Main Road from Madurankuliya.RR/RDA/19/25/26/NWP/PUTAbayarama Mawatha Bomimakka Kovil Road to Sembandaluwa Temple RoadRR/RDA/19/25/28/NWP/PUTSamagi MawathaRR/RDA/19/25/29/NWP/PUTDevelopment of the road from Galkuliya Welameda to Mrs. Deepani's houseRR/RDA/19/25/30/NWP/PUTDevelopment of carpeting from Mihirajthotupola to Serakkuliya 1 on the Serakkuliya main roadRR/RDA/19/25/31/NWP/PUTDevelopment of carpeting from the point where carpeting has stopped on the Tammana main roadRR/RDA/19/25/32/NWP/PUTDevelopment of the Bammeyaya RoadRR/RDA/19/25/33/NWP/PUTDevelopment of the road from near the Sugatarama Temple, Periyakulam to ThalgaswewaRR/RDA/19/25/34/NWP/PUTCarpeting & Development of Bodhirajapura 4th LaneRR/RDA/19/25/03Nawagattegama Rohala Pare sita Thapal Karyalaya Dakwa margaya (Nawagattegama)RR/RDA/19/25/02Concrete development of the road from Hopper Kada junction to Elu Farm.RR/RDA/19/25/35Carpeting & Development of Kolithatissa Mawatha
+1 more…
Click to filter the awarded table
153.8M
153.8 Mn
Total Expenditure (incl. VAT)
Awarded projects15
RR/RDA/19/25/01/NWP/PUTDevelopment of carpeting the Gammedda road up to Anathapara.RR/RDA/19/25/05/NWP/PUTDevelopment of the road from near Mr. Chaminda's house to Boga PathahaRR/RDA/19/25/08/NWP/PUTCarpeting of Velasia Main Road from Madurankuliya.RR/RDA/19/25/26/NWP/PUTAbayarama Mawatha Bomimakka Kovil Road to Sembandaluwa Temple RoadRR/RDA/19/25/28/NWP/PUTSamagi MawathaRR/RDA/19/25/29/NWP/PUTDevelopment of the road from Galkuliya Welameda to Mrs. Deepani's houseRR/RDA/19/25/30/NWP/PUTDevelopment of carpeting from Mihirajthotupola to Serakkuliya 1 on the Serakkuliya main roadRR/RDA/19/25/31/NWP/PUTDevelopment of carpeting from the point where carpeting has stopped on the Tammana main roadRR/RDA/19/25/32/NWP/PUTDevelopment of the Bammeyaya RoadRR/RDA/19/25/33/NWP/PUTDevelopment of the road from near the Sugatarama Temple, Periyakulam to ThalgaswewaRR/RDA/19/25/34/NWP/PUTCarpeting & Development of Bodhirajapura 4th LaneRR/RDA/19/25/03Nawagattegama Rohala Pare sita Thapal Karyalaya Dakwa margaya (Nawagattegama)RR/RDA/19/25/02Concrete development of the road from Hopper Kada junction to Elu Farm.RR/RDA/19/25/35Carpeting & Development of Kolithatissa Mawatha
+1 more…
Click to filter the awarded table
46.7%
0
On Progress
7 / 15 awarded
On Progress (incl. completed)7
RR/RDA/19/25/26/NWP/PUTAbayarama Mawatha Bomimakka Kovil Road to Sembandaluwa Temple RoadRR/RDA/19/25/28/NWP/PUTSamagi MawathaRR/RDA/19/25/29/NWP/PUTDevelopment of the road from Galkuliya Welameda to Mrs. Deepani's houseRR/RDA/19/25/03Nawagattegama Rohala Pare sita Thapal Karyalaya Dakwa margaya (Nawagattegama)RR/RDA/19/25/02Concrete development of the road from Hopper Kada junction to Elu Farm.RR/RDA/19/25/35Carpeting & Development of Kolithatissa Mawatha
+1 more…
Click to filter the awarded table
0%
0
Delay
0 / 15 awarded
Delay0
No projects
Click to filter the awarded table
53.3%
0
Critical Delay
8 / 15 awarded
Critical Delay8
RR/RDA/19/25/01/NWP/PUTDevelopment of carpeting the Gammedda road up to Anathapara.RR/RDA/19/25/05/NWP/PUTDevelopment of the road from near Mr. Chaminda's house to Boga PathahaRR/RDA/19/25/08/NWP/PUTCarpeting of Velasia Main Road from Madurankuliya.RR/RDA/19/25/30/NWP/PUTDevelopment of carpeting from Mihirajthotupola to Serakkuliya 1 on the Serakkuliya main roadRR/RDA/19/25/31/NWP/PUTDevelopment of carpeting from the point where carpeting has stopped on the Tammana main roadRR/RDA/19/25/32/NWP/PUTDevelopment of the Bammeyaya RoadRR/RDA/19/25/33/NWP/PUTDevelopment of the road from near the Sugatarama Temple, Periyakulam to ThalgaswewaRR/RDA/19/25/34/NWP/PUTCarpeting & Development of Bodhirajapura 4th Lane
Click to filter the awarded table
40%
0
Completed
6 / 15 awarded
Completed6
RR/RDA/19/25/26/NWP/PUTAbayarama Mawatha Bomimakka Kovil Road to Sembandaluwa Temple RoadRR/RDA/19/25/28/NWP/PUTSamagi MawathaRR/RDA/19/25/29/NWP/PUTDevelopment of the road from Galkuliya Welameda to Mrs. Deepani's houseRR/RDA/19/25/03Nawagattegama Rohala Pare sita Thapal Karyalaya Dakwa margaya (Nawagattegama)RR/RDA/19/25/02Concrete development of the road from Hopper Kada junction to Elu Farm.RR/RDA/19/25/35Carpeting & Development of Kolithatissa Mawatha
Click to filter the awarded table
Portfolio Breakdown · EE: Puttalam · EE Office
Avg Physical Progress per EE Division · EE: Puttalam
At-Risk Projects · EE: Puttalam
- RR/RDA/19/25/01/NWP/PUTDevelopment of carpeting the Gammedda road up to Anathapara.Delay319 Days in Delay · 65%
- RR/RDA/19/25/05/NWP/PUTDevelopment of the road from near Mr. Chaminda's house to Boga PathahaDelay245 Days in Delay · 65%
- RR/RDA/19/25/08/NWP/PUTCarpeting of Velasia Main Road from Madurankuliya.Delay214 Days in Delay · 70%
- RR/RDA/19/25/30/NWP/PUTDevelopment of carpeting from Mihirajthotupola to Serakkuliya 1 on the Serakkuliya main roadDelay206 Days in Delay · 70%
- RR/RDA/19/25/33/NWP/PUTDevelopment of the road from near the Sugatarama Temple, Periyakulam to ThalgaswewaDelay206 Days in Delay · 45%
- RR/RDA/19/25/32/NWP/PUTDevelopment of the Bammeyaya RoadDelay176 Days in Delay · 50%
- RR/RDA/19/25/34/NWP/PUTCarpeting & Development of Bodhirajapura 4th LaneDelay176 Days in Delay · 70%
- RR/RDA/19/25/31/NWP/PUTDevelopment of carpeting from the point where carpeting has stopped on the Tammana main roadDelay175 Days in Delay · 50%
- Development of the road from Madurankuliya to Velasiya CollegeDelay167 Days in Delay · 30%
Portfolio Timeline· 14 scheduled projects · EE: Puttalam Toggle
2025-06-21 today2026-11-04
Portfolio · Awarded Works
Awarded Projects
6 projects
Filter awarded works
6 matching projects2 active
| # | Contract No. | Package No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|---|---|
| 1 | RR/RDA/19/25/26/NWP/PUT | RR/RDA/19/25/26 | Abayarama Mawatha Bomimakka Kovil Road to Sembandaluwa Temple Road | 100% | 26,275,458.07 | 42,010,632.00 | Awarded |
| 2 | RR/RDA/19/25/28/NWP/PUT | RR/RDA/19/25/28 | Samagi Mawatha | 100% | 25,908,850.00 | 36,001,594.79 | Awarded |
| 3 | RR/RDA/19/25/29/NWP/PUT | RR/RDA/19/25/29 | Development of the road from Galkuliya Welameda to Mrs. Deepani's house | 100% | 8,675,871.60 | 13,481,102.43 | Awarded |
| 4 | RR/RDA/19/25/03 | — | Nawagattegama Rohala Pare sita Thapal Karyalaya Dakwa margaya (Nawagattegama) | 100% | 23,512,239.79 | 23,512,239.79 | Awarded |
| 5 | RR/RDA/19/25/02 | — | Concrete development of the road from Hopper Kada junction to Elu Farm. | 100% | 33,229,489.54 | 33,229,489.54 | Awarded |
| 6 | RR/RDA/19/25/35 | — | Carpeting & Development of Kolithatissa Mawatha | 100% | 10,359,335.01 | 10,359,335.01 | Awarded |
Showing 1–6 of 6
Source: DRRRP • 20 projects • Data updated 2026-11-02 10:30 • 17:20:15 System live • Sri Lanka • 1 districts