DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 27 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:27 awarded · Ratnapura

Portfolio Breakdown · Ratnapura · District

579Awarded739Total
Ratnapura 27 awarded of 37 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn93633%1,181.8225.6155.222.110% of contract66.7%65.0%
Tender Below 50Mn1514193%426.7279.2270.082.329% of contract95.7%98.1%
DL Stage 01330100%113.5113.5113.5104.092% of contract100.0%100.0%
DL Stage 02220100%56.856.856.855.598% of contract100.0%100.0%
DL Stage 03110100%27.827.827.813.950% of contract100.0%100.0%
DL Stage 04440100%335.0335.0335.055.216% of contract100.0%22.5%
PIU2020%0.00.0————
Not Specified1010%0.00.0————
Ratnapura37271073%2,141.61,037.9958.4332.932% of contract94.1%83.7%

Avg Physical Progress per EE Division · Ratnapura

Portfolio Timeline· 26 scheduled projects · Ratnapura Toggle
Portfolio · Awarded Works

Awarded Projects

8 projects

8/8 (filtered)

Filter awarded works

8 matching projects1 active

ActiveIn progress
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/25/24/01/SBP/RTPRR/RDA/25/24/01
From Delgas Junction To Vilehena Road
90%
30,346,327.4143,303,726.54Awarded
2RR/RDA/25/24/02/SBP/RTPRR/RDA/25/24/02
Thundola Varathenna Road
35%
123,540,895.50122,516,687.81Awarded
3RR/RDA/25/24/03/SBP/RTPRR/RDA/25/24/03
From Thunaghahena To Temple Road
95%
20,065,425.8227,753,891.86Awarded
4RR/RDA/25/24/10/SBP/RTPRR/RDA/25/24/10
From Deniya kade Market to Henyaya Road Via Keenagahaella Road
95%
31,673,916.4550,516,461.34Awarded
5RR/RDA/25/24/35—
Ilumba Kanda Road from Milinduthalawa Temple
30%
24,709,638.7124,709,638.71Awarded
6RR/RDA/25/24/17—
Pahalawaththa to Batahenkanda Road
10%
112,040,241.38112,040,241.38Awarded
7RR/RDA/25/24/19—
Wijeriya Iththekanda Margaya Sanwardanaya Kirima
35%
72,158,727.6972,158,727.69Awarded
8RR/RDA/25/24/20—
Godawela Walakada margaya Sanwardanaya Kirima (Walakada Junction to Godawela Junction)
15%
126,132,479.80126,132,479.80Awarded
Showing 1–8 of 8
Per page:
Source: DRRRP • 37 projects • Data updated 2026-11-02 10:30 • 13:38:35