DRRRP Awarded Tender Tender Below 50Mn

RR/RDA/24/25/28/SBP/RTP

From near Kalal Ella Rubber Store to Narangalla via Navinikanda Road

RatnapuraSabaragamuwa ProvincePelmadullaDivisional SecretariatKEP ConstructionContractorLKR 18,880,633.26Contract Sum90 daysProject Duration
0%
Complete
Physical Progress0%
Planned Progress96.9%
Time Elapsed94.4%
On Track • 5 days left

Project Timeline

LOA
2026-07-28
Completed
Possession
–
Pending
Commencement
2026-08-11
Completed
Scheduled Completion
2026-11-09
On Track
Anticipated Completion Date
–
Pending