Monitor financial performance across 117 awarded projects

2026-11-05
04:01:12Live2026-11-05
0 / 117Advance Pendingpending advance projects / total projects
0 / 117IPC Pendingpending IPC projects / total projects
0 / 117Advance Paidadvance paid projects / total projects
0 / 117IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Northern Province · Province

579Projects23,829.3Contract Mn
Northern Province 117 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn383,653.1685.919% of contract2,967.2——————42.1%0.0%
Tender Below 50Mn621,321.6515.639% of contract806.1——————43.5%0.0%
PIU21,460.9—1,460.9——————0.0%0.0%
Tender Total1026,435.61,201.519% of contract5,234.1000.0000.042.1%0.0%
Direct LabourDL Stage 015129.194.673% of contract34.5——————80.0%0.0%
DL Stage 026255.1173.568% of contract81.6——————66.7%0.0%
DL Stage 03285.248.857% of contract36.4——————100.0%0.0%
DL Stage 04238.622.759% of contract15.9——————0.0%0.0%
Direct Labour Total15508.0339.667% of contract168.5000.0000.066.7%0.0%
—Northern Province1176,943.61,541.122% of contract5,402.6000.0000.045.3%0.0%
Tender Above 50Mn38 projectsTender3,653.1Mn
19% paid685.9 Mn
Pending2,967.2Mn
Planned Fin42.1%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn62 projectsTender1,321.6Mn
39% paid515.6 Mn
Pending806.1Mn
Planned Fin43.5%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU2 projectsTender1,460.9Mn
0% paid0.0 Mn
Pending1,460.9Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 015 projectsDirect Labour129.1Mn
73% paid94.6 Mn
Pending34.5Mn
Planned Fin80.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 026 projectsDirect Labour255.1Mn
68% paid173.5 Mn
Pending81.6Mn
Planned Fin66.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 032 projectsDirect Labour85.2Mn
57% paid48.8 Mn
Pending36.4Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 042 projectsDirect Labour38.6Mn
59% paid22.7 Mn
Pending15.9Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Northern Province117 projects6,943.6Mn
22% paid1,541.1 Mn
Pending5,402.6Mn
Planned Fin45.3%
Actual Fin0.0%

Avg Physical Progress per Province · Northern Province

Graphs reflect current view:117 awarded · Northern Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

31–40/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
31RR/RDA/16/25/10KM/03/AKK/AMP
On the road from Pulungasmulla to Padawala, the road from near Shanta Veladasala…
Sawsiri Construction
21,202,726.44————————————
32RR/RDA/16/25/10KM/04/AKK/AMP
Vevinna Boogas Junction Inner Road
Gama Construction & Consultant pvt Ltd
9,692,957.45————————————
33RR/RDA/16/25/10KM/05/AKK/AMP
Road from Dorapaha Junction to Navagiriya Lake
Ema Constructions (Pvt) Ltd
18,058,942.00————————————
34RR/RDA/16/25/10KM/07/AKK/AMP
Bedirakka Malgastalawa Road
Pearl Construction
16,362,791.50————————————
35RR/RDA/16/25/10KM/08/AKK/AKK
RDS Road Addalachena 6, 8
MLH & sons Construction
18,326,682.50————————————
36RR/RDA/16/25/10KM/11/AKK/AKK
Kalyana Road - Periyanilavanai Vishnu Kovil Road to Maradamuna Mashur Maulana Ro…
Zaka Engineering Consultancy
20,596,083.20————————————
37RR/RDA/16/25/10KM/13/AKK/AKK
Jaica - Tsunami Village Road
Gama Construction & Consultant pvt Ltd
26,167,747.32————————————
38RR/RDA/15/25/02/EP/BTC
Concreting to Samurthi 1st Cross road
Kumaran Construction and Civil Works
22,158,474.12————————————
39RR/RDA/15/25/15/EP/BTC
Concrete to the Majma Nagar Mullivattuvan at paper town 210B
KMC Construction
25,270,404.71————————————
40RR/RDA/15/25/05/EP/BTC
Concreting to Mailanthanai Sri Muththumariyamman Main Road
Kumaran Construction and Civil Works
23,225,083.20————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 31–40 of 218 projects · page 4/22