Monitor financial performance across 0 awarded projects

2026-11-05
14:42:06Live2026-11-05
0 / 0Advance Pendingpending advance projects / total projects
0 / 0IPC Pendingpending IPC projects / total projects
0 / 0Advance Paidadvance paid projects / total projects
0 / 0IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

0%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Sabaragamuwa Province · EE: Nuwara Eliya · EE Office

567Projects20,718.2Contract Mn
Nuwara Eliya 6 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn151.83.26% of contract48.5——————100.0%0.0%
Tender Below 50Mn138.84.512% of contract34.3——————100.0%0.0%
DL Stage 01165.376.6117% of contract-11.3——————100.0%0.0%
DL Stage 02140.745.3111% of contract-4.6——————100.0%0.0%
DL Stage 03218.914.476% of contract4.4——————100.0%0.0%
DL Stage 0400.0——————————
Nuwara Eliya6215.5144.167% of contract71.4000.0000.0100.0%0.0%
Tender Above 50Mn1 project51.8Mn
6% paid3.2 Mn
Pending48.5Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn1 project38.8Mn
12% paid4.5 Mn
Pending34.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project65.3Mn
117% paid76.6 Mn
Pending—
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project40.7Mn
111% paid45.3 Mn
Pending—
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 032 projects18.9Mn
76% paid14.4 Mn
Pending4.4Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Nuwara Eliya6 projects215.5Mn
67% paid144.1 Mn
Pending71.4Mn
Planned Fin100.0%
Actual Fin0.0%

Avg Physical Progress per Province · Sabaragamuwa Province · EE: Nuwara Eliya

No province data available

Awarded projects will appear here

Project-wise Financials · Sabaragamuwa Province · EE: Nuwara Eliya (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · Sabaragamuwa Province · EE: Nuwara Eliya (Mn · incl. VAT)

Scroll horizontally — 579 projects

Nuwara Eliya Division · Sabaragamuwa Province · EE: Nuwara Eliya (Mn · incl. VAT)

District District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:0 awarded · Sabaragamuwa Province · EE: Nuwara Eliya
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

151–160/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
151—
Development of the road from the main road to near the Kadawala Wewa School
Nadun Construction (Pvt) Ltd
93,990,000.00————————————
152—
Development of the road from near the house at Pulastigama 156 to Sungawila 1 Ca…
Nadun Construction (Pvt) Ltd
67,120,000.00————————————
153—
Road from near the Wota Gedi Bridge to Dambalu Stores
Nathan's Construction
69,810,000.00————————————
154RR/RDA/18/25/01/NWP/KRG
Development of Egodagama Talakolawewa road
Sri Ram Constructions
98,323,766.14————————————
155RR/RDA/18/25/02/NWP/KRG
Road from Parakumpura to Yaya 04
Ingress Engineering
20,126,522.24————————————
156RR/RDA/18/25/04/NWP/KRG
The road from Hunugallewa road junction to Madadenigama Hunugallewa Mahamaruwa B…
Shanho Enterprises Pvt Ltd.
59,066,766.74————————————
157RR/RDA/18/25/07/NWP/KRG
Road from Moragolla Junction to Nabadewa Girilla Carpet Road via Kirinda
Jayasinghe Constructions (Pvt) Ltd.
59,247,280.29————————————
158RR/RDA/18/25/08/NWP/KRG
Paving of road from Nammuawa to Nagansole temple
Omega Construction (Pvt) Ltd
33,899,382.00————————————
159RR/RDA/18/25/09/NWP/KRG
Paving the road from Pahala Galapitiyagama to Tharanagolla Sports Ground
Senerath Engineering (pvt) Ltd
70,405,428.60————————————
160RR/RDA/18/25/11/NWP/KRG
Development of road from Dambulu Road to Havanathenna via Ehelagollaya
Shanho Enterprises Pvt Ltd.
46,193,949.68————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 151–160 of 579 projects · page 16/58