DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 8 awarded projects

2026-11-04
22:31:42Live2026-11-04
0 / 8Advance Pendingpending advance projects / total projects
0 / 8IPC Pendingpending IPC projects / total projects
0 / 8Advance Paidadvance paid projects / total projects
0 / 8IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Hanguranketha · EE Office

567Projects20,718.2Contract Mn
Hanguranketha 8 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn4222.715.67% of contract207.1——————50.0%0.0%
Tender Below 50Mn131.7—31.7——————100.0%0.0%
DL Stage 01159.763.9107% of contract-4.2——————100.0%0.0%
DL Stage 0200.0——————————
DL Stage 03270.33.65% of contract66.7——————100.0%0.0%
DL Stage 0400.0——————————
Hanguranketha8384.483.122% of contract301.3000.0000.075.0%0.0%
Tender Above 50Mn4 projects222.7Mn
7% paid15.6 Mn
Pending207.1Mn
Planned Fin50.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn1 project31.7Mn
0% paid0.0 Mn
Pending31.7Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project59.7Mn
107% paid63.9 Mn
Pending—
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 020 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 032 projects70.3Mn
5% paid3.6 Mn
Pending66.7Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Hanguranketha8 projects384.4Mn
22% paid83.1 Mn
Pending301.3Mn
Planned Fin75.0%
Actual Fin0.0%

Avg Physical Progress per Province · EE: Hanguranketha

Project-wise Financials · EE: Hanguranketha (291 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Hanguranketha (Mn · incl. VAT)

Scroll horizontally — 291 projects

Hanguranketha Division · EE: Hanguranketha (Mn · incl. VAT)

Nuwara Eliya District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:8 awarded · EE: Hanguranketha
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 291 projects (filtered from 579)

51–60/291 (filtered from 579)
ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
51RR/RDA/20/25/13/NCP/ANP
Maradankadawala Habarana pare kaudawa handiyen patangena rambewa gammanaya dakwa…
Sawsiri Construction
21,609,366.35————————————
52RR/RDA/20/25/14/NCP/ANP
Kukulewa pansala asalin arambavee samadhigama haraha seeppukulama rambewa maraga…
Kumari Konthrathkaruwo
29,296,077.00————————————
53RR/RDA/21/25/04/NCP/POL
10th Canal Lake Road
Nadun Construction (Pvt) Ltd
18,877,127.00————————————
54RR/RDA/18/25/02/NWP/KRG
Road from Parakumpura to Yaya 04
Ingress Engineering
20,126,522.24————————————
55RR/RDA/18/25/08/NWP/KRG
Paving of road from Nammuawa to Nagansole temple
Omega Construction (Pvt) Ltd
33,899,382.00————————————
56RR/RDA/18/25/16/NWP/KRG
Development of concrete road from near Wadawa temple to the lake
Jayawardana Constructions (Pvt) Ltd.
25,583,393.00————————————
57RR/RDA/18/25/24/NWP/KRG
Paving and developing the road from Seelarathana Mawatha to Girana Junction
Senerath Engineering (pvt) Ltd
37,201,129.80————————————
58RR/RDA/18/25/104/NWP/KRG
Pinnagolla Junction to Kokowaththa Junction VIA Alakolapelessa
Senerath Engineering (pvt) Ltd
24,010,872.60————————————
59RR/RDA/18/25/106/NWP/KRG
Thagahinna Temple Road
Jayawansa Construction (PVT) Ltd
13,370,813.50————————————
60RR/RDA/18/25/NWP/KRG/10
Uyandana Yaggapitiya
Senerath Engineering (pvt) Ltd
45,801,928.20————————————
Total8,230,991,569.86——————————
—Mn
0%
—Mn
0%
Showing 51–60 of 291 projects · page 6/30