DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 5 awarded projects

2026-11-04
20:50:48Live2026-11-04
0 / 5Advance Pendingpending advance projects / total projects
0 / 5IPC Pendingpending IPC projects / total projects
0 / 5Advance Paidadvance paid projects / total projects
0 / 5IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Hambantota · EE Office

567Projects20,718.2Contract Mn
Hambantota 5 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn00.0——————————
Tender Below 50Mn00.0——————————
DL Stage 01278.460.377% of contract18.1——————50.0%0.0%
DL Stage 02137.729.779% of contract8.0——————100.0%0.0%
DL Stage 0300.0——————————
DL Stage 042121.3119.899% of contract1.5——————50.0%0.0%
Hambantota5237.4209.888% of contract27.6000.0000.060.0%0.0%
Tender Above 50Mn0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 012 projects78.4Mn
77% paid60.3 Mn
Pending18.1Mn
Planned Fin50.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project37.7Mn
79% paid29.7 Mn
Pending8.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 042 projects121.3Mn
99% paid119.8 Mn
Pending1.5Mn
Planned Fin50.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Hambantota5 projects237.4Mn
88% paid209.8 Mn
Pending27.6Mn
Planned Fin60.0%
Actual Fin0.0%

Avg Physical Progress per Province · EE: Hambantota

Project-wise Financials · EE: Hambantota (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Hambantota (Mn · incl. VAT)

Scroll horizontally — 579 projects

Hambantota Division · EE: Hambantota (Mn · incl. VAT)

Hambantota District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:5 awarded · EE: Hambantota
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

551–560/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
551RR/RDA/23/25/04
Walawegaga Asala (Nildiya Mankada) Sita Udawalawa Bant eka Dakwa
—
74,104,374.63————————————
552RR/RDA/22/25/13
Peessa Pradana Margaye Abalan wu Ellanda Marga Kotasa
—
13,192,586.35————————————
553RR/RDA/22/25/10
Kosgolla Edaru Ulpatha Margaya
—
13,085,885.70————————————
554RR/RDA/23/25/03
Liyangolla Lolla Margaya
—
38,879,897.00————————————
555RR/RDA/23/25/02
Uduwara wewa Handiya sita Athula Margaya
—
34,079,767.34————————————
556RR/RDA/01/25/11
Vijitha Salawa asala sita Kothalawala Vidyalaya Asalin Gothami Viharaya dakva Ma…
—
17,512,654.33————————————
557RR/RDA/01/25/07
428/B Ihala Kosgama Grama Niladhari Wasame Praja Shalawa Pahala Margaya
—
51,557,606.95————————————
558RR/RDA/02/25/02
Development from the road in front of Kanti Teacher's house onwards to Vivekaram…
—
10,523,274.77————————————
559RR/RDA/02/25/01
Heendeniya Dumriya Sthanaya Dakwa Margaya
—
13,144,147.11————————————
560RR/RDA/02/25/04
Delpe Kadawara sita Nelumwaththa margaya arambaye sita Dewadasa mahathage niwasa…
—
26,006,255.54————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 551–560 of 579 projects · page 56/58