DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 19 awarded projects

2026-11-04
23:07:45Live2026-11-04
0 / 19Advance Pendingpending advance projects / total projects
0 / 19IPC Pendingpending IPC projects / total projects
0 / 19Advance Paidadvance paid projects / total projects
0 / 19IPCs PaidIPC paid projects / total projects
849.3 Mn

849.34 Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

11.4%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Colombo · District

579Projects23,829.3Contract Mn
Colombo 19 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn133.67.723% of contract25.9——————0.0%0.0%
Tender Below 50Mn686.618.221% of contract68.4——————0.0%0.0%
DL Stage 01269.162.691% of contract6.4——————100.0%0.0%
DL Stage 02220.08.241% of contract11.8——————100.0%0.0%
DL Stage 0318.06.379% of contract1.7——————100.0%0.0%
DL Stage 047632.2—632.2——————0.0%0.0%
PIU00.0——————————
Colombo19849.3103.012% of contract746.3000.0000.026.3%0.0%
Tender Above 50Mn1 project33.6Mn
23% paid7.7 Mn
Pending25.9Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn6 projects86.6Mn
21% paid18.2 Mn
Pending68.4Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 012 projects69.1Mn
91% paid62.6 Mn
Pending6.4Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projects20.0Mn
41% paid8.2 Mn
Pending11.8Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project8.0Mn
79% paid6.3 Mn
Pending1.7Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 047 projects632.2Mn
0% paid0.0 Mn
Pending632.2Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Colombo19 projects849.3Mn
12% paid103.0 Mn
Pending746.3Mn
Planned Fin26.3%
Actual Fin0.0%

Avg Physical Progress per Province · Colombo

Graphs reflect current view:19 awarded · Colombo
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 291 projects (filtered from 579)

61–70/291 (filtered from 579)
ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
61RR/RDA/18/25/136/NWP/KRG
Ranasinghe Hotel Asalin Koralaya Waththe sita Panwala Kubura Dakwa Diwena Margay…
Jayasinghe Contractors (Pvt) Ltd.
21,718,130.50————————————
62RR/RDA/19/25/26/NWP/PUT
Abayarama Mawatha Bomimakka Kovil Road to Sembandaluwa Temple Road
Sampath Construction
26,275,458.07————————————
63RR/RDA/19/25/28/NWP/PUT
Samagi Mawatha
Ranuja Construction
25,908,850.00————————————
64RR/RDA/19/25/29/NWP/PUT
Development of the road from Galkuliya Welameda to Mrs. Deepani's house
Sampath Construction
8,675,871.60————————————
65RR/RDA/10/25/03/NP/JFN
Navalar Road
KBS Engineering Solution
7,919,722.64————————————
66RR/RDA/10/25/04/NP/JFN
Aluminium Factory Road
Majurathas Building Contractors
36,973,948.00————————————
67RR/RDA/10/25/05/NP/JFN
Renovation of Kokkuruniya Veethy
Majurathas Building Contractors
22,247,557.75————————————
68RR/RDA/10/25/08/NP/JFN
Renovation of Ilanthaikulam Road
KBS Engineering Solution
12,089,810.15————————————
69RR/RDA/10/25/10/NP/JFN
Nayanmar Road
AVP Construction (Pvt) Ltd
17,917,437.01————————————
70RR/RDA/10/25/11/NP/JFN
Amman Road
Thaaru Construction
14,588,981.00————————————
Total8,230,991,569.86——————————
—Mn
0%
—Mn
0%
Showing 61–70 of 291 projects · page 7/30