DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 3 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-04 16:23Live
Graphs reflect current view:3 awarded · Central Province · EE: Nalanda
33.3%
0
On Progress
1 / 3 awarded
On Progress (incl. completed)1
Click to filter the awarded table
33.3%
0
Delay
1 / 3 awarded
Delay1
Click to filter the awarded table
33.3%
0
Critical Delay
1 / 3 awarded
Critical Delay1
Click to filter the awarded table
0%
0
Completed
0 / 3 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · Central Province · EE: Nalanda · EE Office
Avg Physical Progress per EE Division · Central Province · EE: Nalanda
At-Risk Projects · Central Province · EE: Nalanda
Portfolio Timeline· 3 scheduled projects · Central Province · EE: Nalanda Toggle
2026-06-18 today2027-03-04
Portfolio · Awarded Works
Awarded Projects
1 projects
Filter awarded works
1 matching project1 active
| Contract No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|
| RDA/DRP/CEN/MTL/NAL/49 | Rehabilitation /Improvement of Drains,Hard shoulder & Cash barrier at Naula- Elahera- Pallegama- Hettipola Road (B-312) (8+200-61+240) | 70% | 44,706,119.13 | 56,512,677.41 | Awarded |
Showing 1–1 of 1
Source: DRRRP • 6 projects • Data updated 2026-11-04 16:23 • 16:42:16 System live • Sri Lanka • 1 districts