DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 10 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-04 16:23Live
Graphs reflect current view:10 awarded · Central Province · Matale

Portfolio Breakdown · Central Province · Matale · District

57Awarded131Total
Matale 10 awarded of 18 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp ex-VATPlanned %Actual %
Emergency109190%1,571.81,458.11,066.3247.817% of contract73.9%39.8%
DC - Roads5050%1,957.90.0————
DC - Slope31233%707.0372.1——0.0%0.0%
PD(CP) - Slope0000%0.00.0————
Matale1810856%4,236.71,830.21,066.3247.814% of contract66.5%35.8%

Avg Physical Progress per EE Division · Central Province · Matale

Portfolio Timeline· 9 scheduled projects · Central Province · Matale Toggle
Portfolio · Awarded Works

Awarded Projects

10 projects

10/10

Filter awarded works

10 matching projects

Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/MTL/MTL/31R
Rehabilitation / Improvement of Matale - Udupihilla Road (AB026) (0+000 - 6+000)
7.5%
63,704,849.78—Awarded
RDA/DRP/CEN/MTL/MTL/32
Rehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodapitiya - Yatawatta - Dombawela (B-409) (15+030 - 26+800), Palapathwela - Galewela Road B-346)(0+000 - 8+100) Roads
68%
292,279,354.08395,635,536.56Awarded
RDA/DRP/CEN/MTL/MTL/33
Rehabilitation / Improvement of Wattegama Matale Road (5+280 - 13+160) and Ukuwela Railway station (0+000 - 0+190)
30%
165,006,430.79188,777,407.11Awarded
RDA/DRP/CEN/MTL/MTL/35
Rehabilitation / Improvement of Rattota Gammaduwa Road (7+100 - 11+260)
63%
266,607,902.15291,904,507.83Awarded
RDA/DRP/CEN/MTL/MTL/38
Rehabilitation / Improvement of Kalalpitiya Ukuwela Elkaduwa Road (B 180) (0+000 - 13+470)
14%
281,166,339.80304,428,814.88Awarded
RDA/DRP/CEN/MTL/MTL/41
Rehabilitation / Improvement of Matale Illukkumbura Laggala Road (B 274) (4+000 - 18+000)
11%
276,683,432.37265,809,486.28Awarded
RDA/DRP/CEN/MTL/NAL/48R
Rehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)
5%
50,471,466.0842,736,925.80Awarded
RDA/DRP/CEN/MTL/NAL/49
Rehabilitation /Improvement of Drains,Hard shoulder & Cash barrier at Naula- Elahera- Pallegama- Hettipola Road (B-312) (8+200-61+240)
70%
44,706,119.1356,512,677.41Awarded
RDA/DRP/CEN/MTL/NAL/51
Rehabilitation /Improvement of Retaining wall , drains and shoulder construction Bowathenna Access Road (B-064) (0+000-2+410)
90%
17,458,592.7825,992,198.15Awarded
RDA/DC/DRP/SLOPE/CP/MAT/MAT/PACKAGE-23
REHABILITATION OF SELECTED ROAD SECTIONS ON KALALPITIYA UKUWELA-ELKADUWA ROAD (12th KM) AND SLOPE FAILURES DUE TO DITWAH CYCLONE -PACKAGE -23
0%
372,110,778.00337,000,000.00Awarded
Showing 1–10 of 10
Per page:
Source: DRRRP • 18 projects • Data updated 2026-11-04 16:23 • 16:26:46