DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 10 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka. · Team Leader
Updated 2026-11-04 16:23Live
Graphs reflect current view:10 awarded · Team Leader · Nuwara Eliya
100% awarded
0
Awarded
10 total projects in portfolio
Awarded projects10
RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NE/14RDA/DC/DRP/CP/NE/NE/05RDA/DC/DRP/CP/NE/NE/01RDA/DC/DRP/CP/NE/NE/09RDA/DC/DRP/CP/NE/NE/07RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE-31RDA/DC/DRP/SLOPE/CP/NUE/NOR/PACKAGE 33
Click to filter the awarded table
5,232.6M
5,232.6 Mn
Contract Value
Awarded projects10
RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NE/14RDA/DC/DRP/CP/NE/NE/05RDA/DC/DRP/CP/NE/NE/01RDA/DC/DRP/CP/NE/NE/09RDA/DC/DRP/CP/NE/NE/07RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE-31RDA/DC/DRP/SLOPE/CP/NUE/NOR/PACKAGE 33
Click to filter the awarded table
Avg
16%
3
works in progress
0 completed
Avg Progress
Awarded projects10
RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NE/14RDA/DC/DRP/CP/NE/NE/05RDA/DC/DRP/CP/NE/NE/01RDA/DC/DRP/CP/NE/NE/09RDA/DC/DRP/CP/NE/NE/07RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE-31RDA/DC/DRP/SLOPE/CP/NUE/NOR/PACKAGE 33
Click to filter the awarded table
51.4M
51.4 Mn
Total Expenditure (incl. VAT)
Awarded projects10
RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DRP/CEN/NUE/NUE/66Nuwara Eliya Town Road (B331)RDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROADRDA/DC/DRP/CP/NE/NE/14RDA/DC/DRP/CP/NE/NE/05RDA/DC/DRP/CP/NE/NE/01RDA/DC/DRP/CP/NE/NE/09RDA/DC/DRP/CP/NE/NE/07RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE-31RDA/DC/DRP/SLOPE/CP/NUE/NOR/PACKAGE 33
Click to filter the awarded table
20%
0
On Progress
2 / 10 awarded
On Progress (incl. completed)2
RDA/DRP/CEN/NUE/NUE/60RPeradeniya Badulla Chenkaladi Road (A005)RDA/DC/DRP/CP/NE/NE/04LADY MACALUMS DRIVE ROAD
Click to filter the awarded table
0%
0
Delay
0 / 10 awarded
Delay0
No projects
Click to filter the awarded table
10%
0
Critical Delay
1 / 10 awarded
Critical Delay1
Click to filter the awarded table
0%
0
Completed
0 / 10 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · Team Leader · Nuwara Eliya · Consultant
Project-wise Progress · Team Leader · Nuwara Eliya (10 projects in one graph)
Physical Actual vs Planned per project • Click bar to open project
Project-wise Physical Progress: Actual vs Planned (%) · Team Leader · Nuwara Eliya
Average Physical Progress by EE Division · Team Leader · Nuwara Eliya
Average District-wise Physical Progress (Kandy District)
Kandy district baseline — all categories (consultant filter excluded for comparison)
At-Risk Projects · Team Leader · Nuwara Eliya
Portfolio Timeline· 3 scheduled projects · Team Leader · Nuwara Eliya Toggle
2026-05-02 today2028-03-15
Portfolio · Awarded Works
Awarded Projects
2 projects
Filter awarded works
2 matching projects1 active
| Contract No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|
| RDA/DRP/CEN/NUE/NUE/60R | Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850) | 10% | 336,313,078.73 | 338,287,510.33 | Awarded |
| RDA/DC/DRP/CP/NE/NE/04 | REHABILITAION/ IMPROVEMENTS OF LADY MACALUMS DRIVE ROAD (2+850 - 5+600KM) | 1% | 636,338,397.00 | 560,630,000.00 | Awarded |
Showing 1–2 of 2
Source: DRRRP • 10 projects • Data updated 2026-11-04 16:23 • 17:39:32 System live • Sri Lanka • 1 districts