DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 5 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka. · Norwood EE

Updated 2026-11-04 12:46Live
Graphs reflect current view:5 awarded · Norwood EE · Nuwara Eliya

Portfolio Breakdown · Norwood EE · Nuwara Eliya · Consultant

20Awarded20Total
Norwood EE 5 awarded of 5 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %Kick Off PendingMobilization PendingWorks Not Started
Emergency330100%435.8369.1348.234.09% of contract96.0%45.7%———
DC - Roads220100%857.9979.214.4—1.8%14.0%———
DC - Slope0000%0.00.0———————
PD(CP) - Slope0000%0.00.0———————
Norwood EE550100%1,293.71,348.3362.634.03% of contract58.3%33.0%000

Project-wise Progress · Norwood EE · Nuwara Eliya (5 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear

Project-wise Physical Progress: Actual vs Planned (%) · Norwood EE · Nuwara Eliya

Average Physical Progress by EE Division · Norwood EE · Nuwara Eliya

Average District-wise Physical Progress (Nuwara Eliya District)

Nuwara Eliya district baseline — all categories (consultant filter excluded for comparison)

Portfolio Timeline· 5 scheduled projects · Norwood EE · Nuwara Eliya Toggle
Portfolio · Awarded Works

Awarded Projects

2 projects

2/2 (filtered)

Filter awarded works

2 matching projects1 active

ActiveOn Progress
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DC/DRP/CP/NE/NRW/02
REHABILITATION/ IMPROVEMENT OF APPROCH ROAD TO LAXAPANA POWER HOUSE ROAD CH 6+100 - 12+000
9%
374,859,845.10348,620,000.00Awarded
RDA/DC/DRP/CP/NE/NRW/03
REHABILITATION/ IMPROVEMENT TO ROZELLA RAILWAY STATION ROAD (0+000 - 3+300) KM AND WATAWALA RAILWAY STATION ROAD (0+000 - 1+850) KM
19%
604,298,969.28509,310,000.00Awarded
Showing 1–2 of 2
Per page:
Source: DRRRP • 5 projects • Data updated 2026-11-04 12:46 • 14:38:06