DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 3 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka. · Nalanda EE

Updated 2026-11-04 16:23Live
Graphs reflect current view:3 awarded · Nalanda EE · Central Province

Portfolio Breakdown · Nalanda EE · Central Province · Consultant

44Awarded45Total
Nalanda EE 3 awarded of 3 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %Kick Off PendingMobilization PendingWorks Not Started
Emergency330100%125.2112.666.720.218% of contract69.5%55.0%———
DC - Roads0000%0.00.0———————
DC - Slope0000%0.00.0———————
PD(CP) - Slope0000%0.00.0———————
Nalanda EE330100%125.2112.666.720.218% of contract69.5%55.0%000

Project-wise Progress · Nalanda EE · Central Province (3 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear

Project-wise Physical Progress: Actual vs Planned (%) · Nalanda EE · Central Province

Average Physical Progress by EE Division · Nalanda EE · Central Province

Average District-wise Physical Progress (Matale District)

Matale district baseline — all categories (consultant filter excluded for comparison)

Portfolio Timeline· 3 scheduled projects · Nalanda EE · Central Province Toggle
Portfolio · Awarded Works

Awarded Projects

1 projects

1/1 (filtered)

Filter awarded works

1 matching project1 active

ActiveCritical Delay
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/MTL/NAL/49
Rehabilitation /Improvement of Drains,Hard shoulder & Cash barrier at Naula- Elahera- Pallegama- Hettipola Road (B-312) (8+200-61+240)
70%
44,706,119.1356,512,677.41Awarded
Showing 1–1 of 1
Per page:
Source: DRRRP • 3 projects • Data updated 2026-11-04 16:23 • 16:45:47