Project Monitoring Dashboard

Comprehensive overview of 10 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-04 12:46Live
Graphs reflect current view:10 awarded · Matale

Portfolio Breakdown · Matale · District

171Awarded266Total
Matale 10 awarded of 18 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp ex-VATPlanned %Actual %
Emergency109190%1,571.81,458.11,066.3247.817% of contract73.9%39.8%
DC - Roads5050%1,957.90.0————
DC - Slope31233%707.0372.1——0.0%0.0%
PD(CP) - Slope0000%0.00.0————
Matale1810856%4,236.71,830.21,066.3247.814% of contract66.5%35.8%

Avg Physical Progress per EE Division · Matale

Portfolio Timeline· 9 scheduled projects · Matale Toggle
Portfolio · Awarded Works

Awarded Projects

4 projects

4/4 (filtered)

Filter awarded works

4 matching projects1 active

ActiveDelayed only
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/MTL/MTL/32
Rehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodapitiya - Yatawatta - Dombawela (B-409) (15+030 - 26+800), Palapathwela - Galewela Road B-346)(0+000 - 8+100) Roads
68%
292,279,354.08395,635,536.56Awarded
RDA/DRP/CEN/MTL/MTL/33
Rehabilitation / Improvement of Wattegama Matale Road (5+280 - 13+160) and Ukuwela Railway station (0+000 - 0+190)
30%
165,006,430.79188,777,407.11Awarded
RDA/DRP/CEN/MTL/MTL/35
Rehabilitation / Improvement of Rattota Gammaduwa Road (7+100 - 11+260)
63%
266,607,902.15291,904,507.83Awarded
RDA/DRP/CEN/MTL/NAL/51
Rehabilitation /Improvement of Retaining wall , drains and shoulder construction Bowathenna Access Road (B-064) (0+000-2+410)
90%
17,458,592.7825,992,198.15Awarded
Showing 1–4 of 4
Per page:
Source: DRRRP • 18 projects • Data updated 2026-11-04 12:46 • 13:54:34