DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 23 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-04 16:23Live
Graphs reflect current view:23 awarded · Kandy

Portfolio Breakdown · Kandy · District

171Awarded266Total
Kandy 23 awarded of 57 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp ex-VATPlanned %Actual %
Emergency12120100%1,791.61,520.31,105.2279.418% of contract62.1%30.8%
DC - Roads2020%263.60.0————
DC - Slope2632312%10,322.71,154.710.4—0.9%9.3%
PD(CP) - Slope178947%375.7177.7——0.0%0.0%
Kandy57233440%12,753.62,852.81,115.6279.410% of contract32.5%17.3%

Avg Physical Progress per EE Division · Kandy

Portfolio Timeline· 12 scheduled projects · Kandy Toggle
Portfolio · Awarded Works

Awarded Projects

5 projects

5/5 (filtered)

Filter awarded works

5 matching projects2 active

ActiveDelayed onlyCritical Delay
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/KDY/KAD/11
Rehabilitation / Improvement of Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )
26.5%
193,404,194.96275,515,701.42Awarded
RDA/DRP/CEN/KDY/KUN/21
Improvement of Pitiyegedara-Waththegama-Iriyagasthenna Road (0+000-5+400)
12%
257,721,453.96314,486,807.16Awarded
RDA/DRP/CEN/KDY/KUN/22
Improvement to Damaged Road Section on Weeragantota - Randenigala Road. (From CH 19+000 To CH 27+200)
67%
224,968,435.78333,005,906.52Awarded
RDA/DRP/CEN/KDY/KUN/25
Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)
59%
157,909,825.01178,738,774.63Awarded
RDA/DRP/CEN/KDY/KUN/27
Improvement to Structures on Kandy - Jaffna Road 6+500 - 9+910
66%
113,434,139.40122,896,558.88Awarded
Showing 1–5 of 5
Per page:
Source: DRRRP • 57 projects • Data updated 2026-11-04 16:23 • 19:03:35