DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 10 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka. · Team Leader

Updated 2026-11-04 16:23Live
Graphs reflect current view:10 awarded · Team Leader · Nuwara Eliya
0%

0

Delay

0 / 10 awarded

0%

0

Completed

0 / 10 awarded

Portfolio Breakdown · Team Leader · Nuwara Eliya · Consultant

20Awarded20Total
Team Leader 10 awarded of 10 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %Kick Off PendingMobilization PendingWorks Not Started
Emergency220100%543.9498.2180.351.410% of contract52.8%39.5%———
DC - Roads660100%3,362.14,137.5——0.0%0.3%555
DC - Slope220100%536.0597.0——0.0%0.0%222
PD(CP) - Slope0000%0.00.0———————
Team Leader10100100%4,442.05,232.6180.351.41% of contract10.6%8.1%777

Project-wise Progress · Team Leader · Nuwara Eliya (10 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear

Project-wise Physical Progress: Actual vs Planned (%) · Team Leader · Nuwara Eliya

Average Physical Progress by EE Division · Team Leader · Nuwara Eliya

Average District-wise Physical Progress (Kandy District)

Kandy district baseline — all categories (consultant filter excluded for comparison)

Portfolio Timeline· 3 scheduled projects · Team Leader · Nuwara Eliya Toggle
Portfolio · Awarded Works

Awarded Projects

1 projects

1/1 (filtered)

Filter awarded works

1 matching project1 active

ActiveDelayed only
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/NUE/NUE/66
Rehabilitation / Improvement of Nuwara Eliya Town Road (0+000 - 1+695 ) (0+000 - 0+240 )
69%
161,841,095.70205,630,098.81Awarded
Showing 1–1 of 1
Per page:
Source: DRRRP • 10 projects • Data updated 2026-11-04 16:23 • 22:59:13