Financial Dashboard
Monitor financial performance across 6 awarded projects
1,098.34 Mn
Total Contract
23.24 Mn
Advance Paid (excl. VAT)
53.35 Mn
IPCs Paid (excl. VAT)
76.59 Mn
Total Paid (excl. VAT)
90.38 Mn
Total Paid (incl. VAT)
94.71 Mn
Advance Pend (incl. VAT)
— Mn
IPCs Pend (incl. VAT)
185.10 Mn
Total (Paid+Pend) (incl. VAT)
Paid incl + Adv Pend incl + IPC Pend incl
14.3%
Financial Progress (excl. VAT)
Total (Paid+Pend) excl / Contract
71.7%
Planned Financial Progress
Planned share of contract value
Portfolio Breakdown — Financial (Exclusive Vat) · EE: Chilaw · EE Office
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All Provinces | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| North Western Province | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All Districts | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Puttalam | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 129 | 22,610.7 | 4,184.219% of contract | 207.2 | 81 | 78 | 2,556.7 | 122 | 60 | 989.5 | 85.7% | 15.7% |
| DC - Roads | 8 | 5,116.6 | 57.81% of contract | — | 1 | 1 | 49.0 | — | — | — | 0.5% | 1.0% |
| DC - Slope | 10 | 3,258.5 | — | — | — | — | — | — | — | — | 0.3% | 0.0% |
| PD(CP) - Slope | 8 | 177.7 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| All EE Offices | 155 | 31,163.5 | 4,242.014% of contract | 207.2 | 82 | 79 | 2,605.7 | 122 | 60 | 989.5 | 71.4% | 11.5% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,251.4 | 304.624% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 84.3% | 20.6% |
| DC - Roads | 6 | 4,137.5 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Slope | 2 | 734.6 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nuwara Eliya | 14 | 6,123.4 | 304.65% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 36.1% | 4.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 22 | 4,976.9 | 892.818% of contract | — | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Ratnapura | 22 | 4,976.9 | 892.818% of contract | 0.0 | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 19 | 4,275.2 | 951.322% of contract | — | 15 | 15 | 615.2 | 19 | 13 | 190.9 | 92.4% | 18.9% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Badulla | 19 | 4,275.2 | 951.322% of contract | 0.0 | 15 | 15 | 615.2 | 19 | 13 | 190.9 | 92.4% | 18.9% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 10 | 2,440.9 | 548.422% of contract | — | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kegalle | 10 | 2,440.9 | 548.422% of contract | 0.0 | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 369.1 | 34.09% of contract | — | 2 | 2 | 28.9 | — | — | — | 96.0% | 7.8% |
| DC - Roads | 2 | 979.2 | 57.86% of contract | — | 1 | 1 | 49.0 | — | — | — | 1.8% | 5.0% |
| DC - Slope | 2 | 484.8 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Norwood | 7 | 1,833.0 | 91.85% of contract | 0.0 | 3 | 3 | 77.8 | 0 | 0 | 0.0 | 41.7% | 4.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,105.1 | 271.425% of contract | 33.9 | 5 | 5 | 151.1 | 9 | 4 | 79.0 | 73.7% | 20.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 628.9 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 3 | 57.8 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| Kundasale | 12 | 1,791.8 | 271.415% of contract | 33.9 | 5 | 5 | 151.1 | 9 | 4 | 79.0 | 49.1% | 12.8% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,345.4 | 272.220% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 76.2% | 17.1% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 372.1 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Matale | 7 | 1,717.6 | 272.216% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 65.3% | 13.4% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,447.4 | 253.117% of contract | — | 6 | 6 | 214.5 | — | — | — | 100.0% | 14.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Gampaha | 8 | 1,447.4 | 253.117% of contract | 0.0 | 6 | 6 | 214.5 | 0 | 0 | 0.0 | 100.0% | 14.8% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,433.0 | 196.214% of contract | — | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Colombo | 8 | 1,433.0 | 196.214% of contract | 0.0 | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Chilaw | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 768.2 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 72.5% | 7.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kurunegala | 5 | 768.2 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 72.5% | 7.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 610.8 | 93.515% of contract | — | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Anuradhapura | 6 | 610.8 | 93.515% of contract | 0.0 | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 47.8 | 9.219% of contract | — | 1 | 1 | 7.8 | — | — | — | 100.0% | 16.4% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 2 | 512.3 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Hanguranketha | 3 | 560.1 | 9.22% of contract | 0.0 | 1 | 1 | 7.8 | 0 | 0 | 0.0 | 33.3% | 1.4% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 386.7 | — | — | — | — | — | — | — | — | 2.7% | 0.0% |
| PD(CP) - Slope | 4 | 93.8 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| Gampola | 5 | 480.5 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 0.5% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 359.7 | — | — | — | — | — | — | — | — | 2.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Jaffna | 2 | 359.7 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 2.2% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 193.4 | 58.230% of contract | — | 1 | 1 | 33.3 | 4 | 1 | 16.0 | 100.0% | 25.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 139.1 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 1 | 26.1 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| Kadugannawa | 3 | 358.6 | 58.216% of contract | 0.0 | 1 | 1 | 33.3 | 4 | 1 | 16.0 | 33.3% | 13.7% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 235.4 | 64.727% of contract | — | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Polonnaruwa | 5 | 235.4 | 64.727% of contract | 0.0 | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 221.8 | — | — | — | — | — | — | — | — | 19.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kandy | 3 | 221.8 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 19.2% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 160.3 | 59.237% of contract | — | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Monaragala | 2 | 160.3 | 59.237% of contract | 0.0 | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nalanda | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 49.2 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Trincomalee | 1 | 49.2 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 0.0% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 42.8 | — | — | — | — | — | — | — | — | 62.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Vavuniya | 1 | 42.8 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 62.5% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 37.3 | — | — | — | — | — | — | — | — | 81.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Mullaitivu | 1 | 37.3 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 81.5% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 28.4 | — | — | — | — | — | — | — | — | 100.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Galle | 2 | 28.4 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 100.0% | 0.0% |
Advance & IPC
Advance & IPC
Advance & IPC
Advance & IPC
Avg Physical Progress per Province · EE: Chilaw
Financial Progress per Province (Mn) Excluding VAT · EE: Chilaw
Avg Physical Progress per EE Division · EE: Chilaw
Financial Progress per EE Division (Mn) Excluding VAT · EE: Chilaw
District-wise Physical Progress · EE: Chilaw
District-wise Financial Progress (Mn) Excluding VAT · EE: Chilaw
Consultant-wise Physical Progress · EE: Chilaw
Consultant-wise Financial Progress (Mn) Excluding VAT · EE: Chilaw
Project-wise Physical Progress: Actual vs Planned (%) · EE: Chilaw (6)
Project-wise Financial Progress: Actual vs Planned (Mn) Excluding VAT · EE: Chilaw (6)
Project-wise Financials · EE: Chilaw (92 Projects)
Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Chilaw (Mn · incl. VAT)
Scroll horizontally — 92 projects
Chilaw Division · EE: Chilaw (Mn · incl. VAT)
Puttalam District Summary (Mn · incl. VAT)
District baseline — overall all categories (consultant filter excluded for comparison) · amounts incl. VAT
Financial Summary
Advance payments, IPCs & expenditure per awarded project · 92 projects (filtered from 171)
Filter financial register
92 matching projects1 active
| S/N | Contract No | Contract Name | Contractor | Contract (LKR) | Advance Paid (excl. VAT) | Advance Paid (incl. VAT) | Advance Pend (excl. VAT) | Advance Pend (incl. VAT) | IPCs Paid (excl. VAT) | IPCs Paid (incl. VAT) | IPCs Pend (excl. VAT) | IPCs Pend (incl. VAT) | Overall Expenditure (excl. VAT) | Pending Payments (excl. VAT) | Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 91 | RDA/DRP/NCP/POL/POL/11 | Rehabilitation / Improvement and Construction of New Drainage on Polonnaruwa-Tha… | A.D.M Construction | 44,474,738.82 | 7,582,108.44 | 8,946,887.96 | — | — | — | — | — | — | 7,582,108.44 | — | 8.95Mn Watch20.1% | 8.95Mn 20.1% |
| 92 | RDA/DRP/SP/GAL/HIN/03 | Rehabilitation / Improvement of Gabbion Walls along Udugama - Hiniduma (9+920-… | Ceylon Construction Industry Development… | 19,453,314.54 | — | — | — | — | — | — | — | — | — | — | — | — |
| Total | 16,799,029,680.14 | 2,276,780,837.16 | 2,686,401,372.89 | — | — | 905,188,809.07 | 1,068,036,979.06 | 52,935,451.96 | 60,777,795.94 | 3,181,969,646.23 | 52,935,451.96 | 3,754.44Mn 22.3% | 3,815.22Mn 22.7% | |||