Project Monitoring Dashboard
Comprehensive overview of 8 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-02 10:30Live
Graphs reflect current view:8 awarded · Central Province · EE: Hanguranketha
72.7% awarded
0
Awarded
11 total projects 11 roads in portfolio
Awarded projects8
RR/RDA/06/25/34/CP/NEUdupussellawa margaye Amasta handiye sita Ambagasdowa dakwa MargayaRR/RDA/06/25/38/CP/NEKetahira Gallella margya palama haraha Udagama dakwa MargayaRR/RDA/06/25/40/CP/NEWalapane Samachaithya asalin Arambawana Kurundu oya diyaella dakwa MargayaRR/RDA/06/25/33Mool oya Main Road Section 1RR/RDA/06/25/44Carpeting of Muloya Main Road Section 2RR/RDA/06/25/47Carpeting of the road from Gatakula to Madanwala via Diaudagama, Kottala
+2 more…
Click to filter the awarded table
384.4M
384.4 Mn
Contract Value
Awarded projects8
RR/RDA/06/25/34/CP/NEUdupussellawa margaye Amasta handiye sita Ambagasdowa dakwa MargayaRR/RDA/06/25/38/CP/NEKetahira Gallella margya palama haraha Udagama dakwa MargayaRR/RDA/06/25/40/CP/NEWalapane Samachaithya asalin Arambawana Kurundu oya diyaella dakwa MargayaRR/RDA/06/25/33Mool oya Main Road Section 1RR/RDA/06/25/44Carpeting of Muloya Main Road Section 2RR/RDA/06/25/47Carpeting of the road from Gatakula to Madanwala via Diaudagama, Kottala
+2 more…
Click to filter the awarded table
Avg
48.5%
5
works in progress
1 completed
Avg Progress
Awarded projects8
RR/RDA/06/25/34/CP/NEUdupussellawa margaye Amasta handiye sita Ambagasdowa dakwa MargayaRR/RDA/06/25/38/CP/NEKetahira Gallella margya palama haraha Udagama dakwa MargayaRR/RDA/06/25/40/CP/NEWalapane Samachaithya asalin Arambawana Kurundu oya diyaella dakwa MargayaRR/RDA/06/25/33Mool oya Main Road Section 1RR/RDA/06/25/44Carpeting of Muloya Main Road Section 2RR/RDA/06/25/47Carpeting of the road from Gatakula to Madanwala via Diaudagama, Kottala
+2 more…
Click to filter the awarded table
83.1M
83.1 Mn
Total Expenditure (incl. VAT)
Awarded projects8
RR/RDA/06/25/34/CP/NEUdupussellawa margaye Amasta handiye sita Ambagasdowa dakwa MargayaRR/RDA/06/25/38/CP/NEKetahira Gallella margya palama haraha Udagama dakwa MargayaRR/RDA/06/25/40/CP/NEWalapane Samachaithya asalin Arambawana Kurundu oya diyaella dakwa MargayaRR/RDA/06/25/33Mool oya Main Road Section 1RR/RDA/06/25/44Carpeting of Muloya Main Road Section 2RR/RDA/06/25/47Carpeting of the road from Gatakula to Madanwala via Diaudagama, Kottala
+2 more…
Click to filter the awarded table
37.5%
0
On Progress
3 / 8 awarded
On Progress (incl. completed)3
+2 more…
Click to filter the awarded table
0%
0
Delay
0 / 8 awarded
Delay0
No projects
Click to filter the awarded table
62.5%
0
Critical Delay
5 / 8 awarded
Critical Delay5
RR/RDA/06/25/34/CP/NEUdupussellawa margaye Amasta handiye sita Ambagasdowa dakwa MargayaRR/RDA/06/25/38/CP/NEKetahira Gallella margya palama haraha Udagama dakwa MargayaRR/RDA/06/25/40/CP/NEWalapane Samachaithya asalin Arambawana Kurundu oya diyaella dakwa MargayaRR/RDA/06/25/44Carpeting of Muloya Main Road Section 2RR/RDA/06/25/47Carpeting of the road from Gatakula to Madanwala via Diaudagama, Kottala
Click to filter the awarded table
Portfolio Breakdown · Central Province · EE: Hanguranketha · EE Office
Avg Physical Progress per EE Division · Central Province · EE: Hanguranketha
At-Risk Projects · Central Province · EE: Hanguranketha
- RR/RDA/06/25/44Carpeting of Muloya Main Road Section 2Delay308 Days in Delay · 60%
- RR/RDA/06/25/47Carpeting of the road from Gatakula to Madanwala via Diaudagama, KottalaDelay308 Days in Delay · 38%
- RR/RDA/06/25/40/CP/NEWalapane Samachaithya asalin Arambawana Kurundu oya diyaella dakwa MargayaDelay299 Days in Delay · 10%
- RR/RDA/06/25/34/CP/NEUdupussellawa margaye Amasta handiye sita Ambagasdowa dakwa MargayaDelay182 Days in Delay · 0%
- RR/RDA/06/25/38/CP/NEKetahira Gallella margya palama haraha Udagama dakwa MargayaDelay182 Days in Delay · 0%
- Carpeting of road from Bambaragama Moragollahinna to KaramidulaDelay152 Days in Delay · 10%
- Carpeting of Mahathenna to Hapugasdeniya Main RoadDelay152 Days in Delay · 73%
Portfolio Timeline· 8 scheduled projects · Central Province · EE: Hanguranketha Toggle
2025-06-21 today2026-11-04
Portfolio · Awarded Works
Awarded Projects
1 projects
Filter awarded works
1 matching project1 active
| # | Contract No. | Package No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|---|---|
| 1 | RR/RDA/06/25/33 | — | Mool oya Main Road Section 1 | 100% | 59,668,203.37 | 59,668,203.37 | Awarded |
Showing 1–1 of 1
Source: DRRRP • 11 projects • Data updated 2026-11-02 10:30 • 14:26:13 System live • Sri Lanka • 1 districts