Portfolio Breakdown · EE: Nalanda · EE Office

567Awarded667Total
Nalanda 9 awarded of 11 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn330100%240.8208.4115.734.617% of contract66.7%65.0%
Tender Below 50Mn330100%128.587.635.879.791% of contract33.3%86.7%
DL Stage 01110100%35.735.735.725.070% of contract100.0%100.0%
DL Stage 020000%0.00.0————
DL Stage 03110100%28.428.428.4—100.0%60.0%
DL Stage 04110100%56.256.256.218.834% of contract100.0%75.0%
Not Specified2020%209.30.0————
Nalanda119282%698.9416.4271.8158.238% of contract66.7%76.7%

Avg Physical Progress per EE Division · EE: Nalanda

Portfolio Timeline· 9 scheduled projects · EE: Nalanda Toggle
Portfolio · Awarded Works

Awarded Projects

5 projects

5/5 (filtered)

Filter awarded works

5 matching projects1 active

ActiveDelayed only
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/05/25/10/CP/MTLRR/RDA/05/25/10
Sonuththa pradana margaye Shailatharamaya idiriye sita 80 yaya dakwa
70%
56,167,707.7579,104,652.30Awarded
2RR/RDA/05/25/26/CP/MTLRR/RDA/05/25/26
Pallepola saukya karyalaye sita ekamuthugama dakwa margaya
60%
18,760,083.5430,575,367.23Awarded
3RR/RDA/05/25/30/CP/MTLRR/RDA/05/25/30
Ganadewi pilimaya asala Kulathunga mahathage welanda sala dakwa
60%
59,540,000.0077,270,301.29Awarded
4RR/RDA/05/25/23—
Manchanayake shed eka asala sita sampath waththa haraha Galketiyawa margaya
60%
28,401,905.1228,401,905.12Awarded
5RR/RDA/05/25/28—
Adawala Udagama Road
75%
56,161,142.6856,161,142.68Awarded
Showing 1–5 of 5