Portfolio Breakdown · EE: Norwood · EE Office

567Awarded667Total
Norwood 4 awarded of 8 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn51420%636.3220.1220.193.142% of contract100.0%50.0%
Tender Below 50Mn110100%31.728.328.342.5150% of contract100.0%100.0%
DL Stage 01110100%60.359.359.345.677% of contract100.0%100.0%
DL Stage 020000%0.00.0————
DL Stage 03110100%37.537.537.542.1112% of contract100.0%100.0%
DL Stage 040000%0.00.0————
Not Specified0000%0.00.0————
Norwood84450%765.7345.2345.2223.365% of contract100.0%87.5%

Avg Physical Progress per EE Division · EE: Norwood

Portfolio Timeline· 4 scheduled projects · EE: Norwood Toggle
Portfolio · Awarded Works

Awarded Projects

3 projects

3/3 (filtered)

Filter awarded works

3 matching projects1 active

ActiveProgress 100–100%
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/06/25/37/CP/NERR/RDA/06/25/37
Gewal wissa handiye sita Bogalkanda dakwa Margaye asiru sthan
100%
28,282,100.0031,658,635.80Awarded
2RR/RDA/06/25/35—
Gaminipura Road
100%
59,292,443.8060,272,506.06Awarded
3RR/RDA/06/25/43—
Development of Ponnagar Road
100%
37,481,052.8137,481,052.81Awarded