Project Monitoring Dashboard

Comprehensive overview of 18 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:18 awarded · Badulla
0%

0

Delay

0 / 18 awarded

0%

0

Critical Delay

0 / 18 awarded

Portfolio Breakdown · Badulla · District

579Awarded739Total
Badulla 18 awarded of 18 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn110100%54.638.5—24.163% of contract0.0%10.0%
Tender Below 50Mn11110100%242.4176.257.5125.671% of contract27.3%92.0%
DL Stage 01440100%139.7139.7139.7102.874% of contract100.0%100.0%
DL Stage 02220100%26.326.3—29.3111% of contract0.0%100.0%
DL Stage 030000%0.00.0————
DL Stage 040000%0.00.0————
PIU0000%0.00.0————
Not Specified0000%0.00.0————
Badulla18180100%463.0380.7197.2281.874% of contract38.9%90.1%

Avg Physical Progress per EE Division · Badulla

Portfolio Timeline· 15 scheduled projects · Badulla Toggle
Portfolio · Awarded Works

Awarded Projects

15 projects

15/15 (filtered)

Filter awarded works

15 matching projects1 active

ActiveProgress 100–100%
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/22/25/01/UP/BDLRR/RDA/22/25/01
Kirikoonthenna Gamata piwisena Margaya
100%
15,276,800.0022,562,884.94Awarded
2RR/RDA/22/25/02/UP/BDLRR/RDA/22/25/02
23 Ela Krushi Margaya
100%
22,422,274.0534,734,403.93Awarded
3RR/RDA/22/25/04/UP/BDLRR/RDA/22/25/04
Buluwa Margaya
100%
19,800,000.0027,796,703.13Awarded
4RR/RDA/22/25/08/UP/BDLRR/RDA/22/25/08
Maragaha ella Margaya Concrete Kireema
100%
5,650,802.309,166,668.15Awarded
5RR/RDA/22/25/12/UP/BDLRR/RDA/22/25/12
Galwelagama Margaye Pansala Asala Kotasa
100%
16,955,320.7819,698,086.11Awarded
6RR/RDA/22/25/14/UP/BDLRR/RDA/22/25/14
Pulleyar Kadura sita Keselwaththa Dakwa Piwisena Athrur Margaya
100%
6,085,915.007,780,120.14Awarded
7RR/RDA/22/25/15/UP/BDLRR/RDA/22/25/15
Gallulla sita Galwelagama Margaya
100%
15,696,340.0019,949,882.12Awarded
8RR/RDA/22/25/18/UP/BDLRR/RDA/22/25/18
Pelgahathenna Vidyalaya asalin Landewela dakwa athi Margaya
100%
5,317,232.006,839,881.74Awarded
9RR/RDA/22/25/19/UP/BDLRR/RDA/22/25/19
Tholabowaththa sita Meedumpitiya Dakwa yana Athuru Margaya
100%
30,478,561.7447,901,120.62Awarded
10RR/RDA/22/25/32—
Asphalt laying and Development of Haddaththawa 80 Acre road
100%
93,242,250.1493,242,250.14Awarded
11RR/RDA/22/25/03—
Hubaslinda Meda Margaya
100%
19,159,838.8419,159,838.84Awarded
12RR/RDA/22/25/16—
Dameria Handiye sita wathu Karyalaya Dakwa Margaya
100%
12,215,323.9212,215,323.92Awarded
13RR/RDA/22/26/01—
Rajamawatha Road
100%
15,077,652.8415,077,652.84Awarded
14RR/RDA/22/25/13—
Peessa Pradana Margaye Abalan wu Ellanda Marga Kotasa
100%
13,192,586.3513,192,586.35Awarded
15RR/RDA/22/25/10—
Kosgolla Edaru Ulpatha Margaya
100%
13,085,885.7013,085,885.70Awarded
Showing 1–15 of 15
Per page:
Source: DRRRP • 18 projects • Data updated 2026-11-02 10:30 • 17:16:57