DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 23 awarded projects

2026-11-05
03:31:26Live2026-11-05
0 / 23Advance Pendingpending advance projects / total projects
0 / 23IPC Pendingpending IPC projects / total projects
0 / 23Advance Paidadvance paid projects / total projects
0 / 23IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Uva Province · Province

579Projects23,829.3Contract Mn
Uva Province 23 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn272.658.380% of contract14.3——————0.0%0.0%
Tender Below 50Mn11176.2125.671% of contract50.7——————27.3%0.0%
PIU00.0——————————
Tender Total13248.8183.974% of contract65.0000.0000.023.1%0.0%
Direct LabourDL Stage 016278.4226.881% of contract51.6——————100.0%0.0%
DL Stage 02499.299.1100% of contract0.1——————0.0%0.0%
DL Stage 0300.0——————————
DL Stage 0400.0——————————
Direct Labour Total10377.6325.986% of contract51.7000.0000.060.0%0.0%
—Uva Province23626.4509.881% of contract116.6000.0000.039.1%0.0%
Tender Above 50Mn2 projectsTender72.6Mn
80% paid58.3 Mn
Pending14.3Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn11 projectsTender176.2Mn
71% paid125.6 Mn
Pending50.7Mn
Planned Fin27.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projectsTender0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 016 projectsDirect Labour278.4Mn
81% paid226.8 Mn
Pending51.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 024 projectsDirect Labour99.2Mn
100% paid99.1 Mn
Pending0.1Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projectsDirect Labour0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projectsDirect Labour0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Uva Province23 projects626.4Mn
81% paid509.8 Mn
Pending116.6Mn
Planned Fin39.1%
Actual Fin0.0%

Avg Physical Progress per Province · Uva Province

Graphs reflect current view:23 awarded · Uva Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

81–90/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
81RR/RDA/15/25/11/EP/BTC
Concreting to Kali Kovil Road
Jeezan Trading and Transport
14,105,564.00————————————
82RR/RDA/15/25/12/EP/BTC
Concreting to Muthalaikuda to Munnaikkadu Boundary Road
Kumaran Construction and Civil Works
26,564,874.51————————————
83RR/RDA/15/25/13/EP/BTC
Concreting to Sangarpuram- Vilavadi
Kumaran Construction and Civil Works
24,189,660.00————————————
84RR/RDA/15/25/14/EP/BTC
Concreting to Agriculture Road
Jeezan Trading and Transport
10,593,750.00————————————
85RR/RDA/15/25/10KM/01/BTC
Sooriya farm Road sathurukondan
Ganan Construction
20,565,497.24————————————
86RR/RDA/15/25/10KM/02/BTC
Iruthayapuram west 8th cross
Sanju Civil Construction
27,156,544.25————————————
87RR/RDA/15/25/10KM/06/BTC
Al Ameen Vidyaya Road
Nathan's Construction
32,841,084.21————————————
88RR/RDA/15/25/10KM/07/BTC
Kanady cross Road to Magalingeshwarar kovil Road
Motec Engineering & Construction
25,946,118.00————————————
89RR/RDA/15/25/10KM/08/BTC
Poosakar Road, Kannakipuram, Mahiloor
Nathan's Construction
27,673,151.00————————————
90RR/RDA/17/25/01/EP/TRN
Pillayar Road Renovation
Rina Construction
23,425,921.56————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 81–90 of 579 projects · page 9/58