DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 55 awarded projects

2026-11-05
20:18:30Live2026-11-05
0 / 55Advance Pendingpending advance projects / total projects
0 / 55IPC Pendingpending IPC projects / total projects
0 / 55Advance Paidadvance paid projects / total projects
0 / 55IPCs PaidIPC paid projects / total projects
2,249.3 Mn

2,249.31 Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

17.1%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Western Province · Province

579Projects23,829.3Contract Mn
Western Province 55 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn4207.010.45% of contract196.5——————0.0%0.0%
Tender Below 50Mn26391.794.824% of contract296.9——————30.8%0.0%
PIU1659.1—659.1——————0.0%0.0%
Tender Total311,257.7105.28% of contract1,152.5000.0000.025.8%0.0%
Direct LabourDL Stage 018211.8170.580% of contract41.4——————100.0%0.0%
DL Stage 02334.719.657% of contract15.0——————100.0%0.0%
DL Stage 03473.541.456% of contract32.1——————50.0%0.0%
DL Stage 049671.618.73% of contract653.0——————11.1%0.0%
Direct Labour Total24991.6250.125% of contract741.5000.0000.058.3%0.0%
—Western Province552,249.3355.416% of contract1,894.0000.0000.040.0%0.0%
Tender Above 50Mn4 projectsTender207.0Mn
5% paid10.4 Mn
Pending196.5Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn26 projectsTender391.7Mn
24% paid94.8 Mn
Pending296.9Mn
Planned Fin30.8%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU1 projectTender659.1Mn
0% paid0.0 Mn
Pending659.1Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 018 projectsDirect Labour211.8Mn
80% paid170.5 Mn
Pending41.4Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 023 projectsDirect Labour34.7Mn
57% paid19.6 Mn
Pending15.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 034 projectsDirect Labour73.5Mn
56% paid41.4 Mn
Pending32.1Mn
Planned Fin50.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 049 projectsDirect Labour671.6Mn
3% paid18.7 Mn
Pending653.0Mn
Planned Fin11.1%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Western Province55 projects2,249.3Mn
16% paid355.4 Mn
Pending1,894.0Mn
Planned Fin40.0%
Actual Fin0.0%

Avg Physical Progress per Province · Western Province

Graphs reflect current view:55 awarded · Western Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

301–310/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
301RR/RDA/25/24/14/SBP/RTP
Pimbura- Peelwatta Road
SSP Engineering
15,010,646.74————————————
302RR/RDA/25/24/16/SBP/RTP
Kalawana Salgaha Yata Road
SSP Engineering
34,292,579.12————————————
303RR/RDA/24/25/21/SBP/RTP
Sudagala Grama Seva Division, From Sudagala to Tunudola Road up the mountain to …
DKS Construction
35,222,472.34————————————
304RR/RDA/24/25/25/SBP/RTP
From the point where the Bulathgama-Pallevela road starts from Rasagala Road
Sathira Construction
7,273,850.00————————————
305RR/RDA/24/25/28/SBP/RTP
From near Kalal Ella Rubber Store to Narangalla via Navinikanda Road
KEP Construction
18,880,633.26————————————
306RR/RDA/24/25/31/SBP/RTP
Development of Koratuwegoda Road from Main Road
KEP Construction
19,882,000.02————————————
307RR/RDA/24/25/32/SBP/RTP
Weligepola to Nitta Kumbura Road
Sasiri Construction
14,421,268.00————————————
308RR/RDA/24/25/34/SBP/RTP
Matuwagala Mudun Kotu Road
DKS Construction
—————————————
309RR/RDA/24/25/35/SBP/RTP
Induruwa Junction to Kadawatha junction road joining Kuruwita - Siripagama road
Creates Consultant and Construction
70,340,000.00————————————
310RR/RDA/25/25/02/SBP/KGL
Elagapitiya Colany Road From Debathgama Pallebage to Tea Shakthi Praja Shalawa
EHL Constructions
36,210,751.61————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 301–310 of 579 projects · page 31/58