DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 7 awarded projects

2026-11-04
19:06:54Live2026-11-04
0 / 7Advance Pendingpending advance projects / total projects
0 / 7IPC Pendingpending IPC projects / total projects
0 / 7Advance Paidadvance paid projects / total projects
0 / 7IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Kadugannawa · EE Office

567Projects20,718.2Contract Mn
Kadugannawa 7 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn00.0——————————
Tender Below 50Mn461.127.345% of contract33.8——————100.0%0.0%
DL Stage 01119.316.686% of contract2.7——————100.0%0.0%
DL Stage 02161.339.064% of contract22.3——————100.0%0.0%
DL Stage 03113.910.475% of contract3.5——————100.0%0.0%
DL Stage 0400.0——————————
Kadugannawa7155.593.360% of contract62.2000.0000.0100.0%0.0%
Tender Above 50Mn0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn4 projects61.1Mn
45% paid27.3 Mn
Pending33.8Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project19.3Mn
86% paid16.6 Mn
Pending2.7Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project61.3Mn
64% paid39.0 Mn
Pending22.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project13.9Mn
75% paid10.4 Mn
Pending3.5Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Kadugannawa7 projects155.5Mn
60% paid93.3 Mn
Pending62.2Mn
Planned Fin100.0%
Actual Fin0.0%

Avg Physical Progress per Province · EE: Kadugannawa

Project-wise Financials · EE: Kadugannawa (291 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Kadugannawa (Mn · incl. VAT)

Scroll horizontally — 291 projects

Kadugannawa Division · EE: Kadugannawa (Mn · incl. VAT)

Kandy District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:7 awarded · EE: Kadugannawa
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 291 projects (filtered from 579)

21–30/291 (filtered from 579)
ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
21RR/RDA/05/25/19/CP/MTL
Katudeniya bahukarya godanagilla asala Hettiyawatta dakwa margaya
Ajith Construction
13,129,506.50————————————
22RR/RDA/05/25/20/CP/MTL
Harispattuwa margaya arambaka mansandiye sita Thusitha maranadara godanagilla da…
Ajith Construction
15,584,937.50————————————
23RR/RDA/05/25/22/CP/MTL
Sigirimulla sita Mailetthewa Aluthyaya dakwa margaya
Asiri Contractor and Designers
33,057,264.90————————————
24RR/RDA/05/25/24/CP/MTL
Pahala Hombawa palama dakwa Daduwagolla kanaththa langa sita
Ajith Construction
35,817,952.50————————————
25RR/RDA/05/25/27/CP/MTL
Welemulla sita Kandewaththa
Ajith Construction
23,207,525.00————————————
26RR/RDA/05/25/29/CP/MTL
Pitawala handiye sita pitawala desata
Lahiru Construction & Consultants (PVT) …
37,136,372.90————————————
27RR/RDA/06/25/37/CP/NE
Gewal wissa handiye sita Bogalkanda dakwa Margaye asiru sthan
Ajith Construction
28,282,100.00————————————
28RR/RDA/16/25/04/AKK/AMP
Pokunugama near Mr. Dinesh Tharaga House to Road (From Pokunugama Pre School to …
Harischandra Idikirim
6,435,000.00————————————
29RR/RDA/16/25/01/AKK/AMP
Samanalathenna- Road from House No.63 To the Monastery Muwagammana -From First L…
Vithu Construction
21,336,681.87————————————
30RR/RDA/STA II/16/25/02/AKK/A…
Concreting entrance road with culvert at Dehiaththakandiya Kelegama
Vithu Construction
30,737,790.60————————————
Total8,230,991,569.86——————————
—Mn
0%
—Mn
0%
Showing 21–30 of 291 projects · page 3/30