DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 9 awarded projects

2026-11-05
04:21:05Live2026-11-05
0 / 9Advance Pendingpending advance projects / total projects
0 / 9IPC Pendingpending IPC projects / total projects
0 / 9Advance Paidadvance paid projects / total projects
0 / 9IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · EE: Gampola · EE Office

567Projects20,718.2Contract Mn
Gampola 9 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn2102.011.411% of contract90.6——————99.1%0.0%
Tender Below 50Mn5120.066.756% of contract53.3——————80.0%0.0%
DL Stage 01129.020.972% of contract8.1——————100.0%0.0%
DL Stage 02121.313.764% of contract7.6——————100.0%0.0%
DL Stage 0300.0——————————
DL Stage 0400.0——————————
Gampola9272.3112.741% of contract159.6000.0000.088.7%0.0%
Tender Above 50Mn2 projects102.0Mn
11% paid11.4 Mn
Pending90.6Mn
Planned Fin99.1%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn5 projects120.0Mn
56% paid66.7 Mn
Pending53.3Mn
Planned Fin80.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project29.0Mn
72% paid20.9 Mn
Pending8.1Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project21.3Mn
64% paid13.7 Mn
Pending7.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Gampola9 projects272.3Mn
41% paid112.7 Mn
Pending159.6Mn
Planned Fin88.7%
Actual Fin0.0%

Avg Physical Progress per Province · EE: Gampola

Project-wise Financials · EE: Gampola (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · EE: Gampola (Mn · incl. VAT)

Scroll horizontally — 579 projects

Gampola Division · EE: Gampola (Mn · incl. VAT)

Kandy District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:9 awarded · EE: Gampola
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

91–100/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
91RR/RDA/17/25/02/EP/TRN
Kathirkamathambi Road
Fareed
28,809,738.00————————————
92RR/RDA/17/25/03/EP/TRN
Hospital Road
Pragash Construction
18,557,253.77————————————
93RR/RDA/17/25/05/EP/TRN
Improvement to Jeyanthiwewa to Track 12 Main Road
Nirupama Construction
103,260,000.00————————————
94RR/RDA/17/25/06/EP/TRN
Malporuwa to Thalgaswewa
Jeezan Trading and Transport
109,630,000.00————————————
95RR/RDA/17/25/07/EP/TRN
Kanthamalawa Main Road
SSK Construction
9,161,570.00————————————
96RR/RDA/17/25/09/EP/TRN
School-Galmetiyawa Main Internal Road
Zaka Engineering Consultancy
53,122,107.50————————————
97RR/RDA/17/25/10/EP/TRN
From Medagama temple to Peramaduwa
Soyuru Sampath Construction & Suppliers
24,197,635.00————————————
98RR/RDA/17/25/11/EP/TRN
Development of Road from near the Fair
MS Construction
25,280,343.60————————————
99RR/RDA/17/25/12/EP/TRN
Improvement of RDS Road
MTA Construction
30,166,053.00————————————
100RR/RDA/17/25/13/EP/TRN
Concreting from School junction to Boovidya Office
Hana Construction (Pvt) Ltd.
38,264,100.00————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 91–100 of 579 projects · page 10/58