DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 23 awarded projects

2026-11-05
03:04:12Live2026-11-05
0 / 23Advance Pendingpending advance projects / total projects
0 / 23IPC Pendingpending IPC projects / total projects
0 / 23Advance Paidadvance paid projects / total projects
0 / 23IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Kegalle · District

579Projects23,829.3Contract Mn
Kegalle 23 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn3210.0132.163% of contract77.9——————66.7%0.0%
Tender Below 50Mn15355.0113.532% of contract241.5——————66.7%0.0%
DL Stage 01271.037.753% of contract33.3——————100.0%0.0%
DL Stage 02263.047.475% of contract15.6——————100.0%0.0%
DL Stage 0317.00.913% of contract6.1——————100.0%0.0%
DL Stage 0400.0——————————
PIU00.0——————————
Kegalle23706.0331.747% of contract374.3000.0000.073.9%0.0%
Tender Above 50Mn3 projects210.0Mn
63% paid132.1 Mn
Pending77.9Mn
Planned Fin66.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn15 projects355.0Mn
32% paid113.5 Mn
Pending241.5Mn
Planned Fin66.7%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 012 projects71.0Mn
53% paid37.7 Mn
Pending33.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projects63.0Mn
75% paid47.4 Mn
Pending15.6Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project7.0Mn
13% paid0.9 Mn
Pending6.1Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Kegalle23 projects706.0Mn
47% paid331.7 Mn
Pending374.3Mn
Planned Fin73.9%
Actual Fin0.0%

Avg Physical Progress per Province · Kegalle

Graphs reflect current view:23 awarded · Kegalle
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

61–70/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
61RR/RDA/20/25/06/NCP/ANP
Ududumbara boogas handiye sita sarakkugala pasal handiya dakwa margaya
Dissanayaka Builders
26,692,661.01————————————
62RR/RDA/20/25/11/NCP/ANP
Palayakulama sita halmillakulama dakwa margaya
Dissanayaka Builders
20,887,268.20————————————
63RR/RDA/20/25/16/NCP/ANP
Hiriwadunna handiye sita idigaswewa pansal handiya dakwa margaya
Sun Constructions (Pvt) Ltd.
33,000,000.00————————————
64RR/RDA/20/25/18/NCP/ANP
Pahala Talawa road of Thalawa Andarawewa road
HPS Construction
32,443,580.50————————————
65RR/RDA/20/25/26/NCP/ANP
Development of IV lane from Nuwara Road to Mihinthalaya Road
Priyantha Civil Engineering
29,650,453.29————————————
66RR/RDA/20/25/28/NCP/ANP
Development of Rathnayake Mawatha
Priyantha Civil Engineering
23,041,750.80————————————
67RR/RDA/20/25/29/NCP/ANP
Development of the road from Udugama Colony rural road near the A9 road to the f…
Priyantha Civil Engineering
27,986,392.06————————————
68—
Development of road from Sripura main road to 38 Kolaniya Cemetery
NMST Contractor
27,971,333.13————————————
69—
Development of road from Wahalkada D6 to Thalapakattialam on Punchimudagama road
Priyantha Civil Engineering
33,242,915.64————————————
70—
Development of first phase of road from Punewa to Warakwewa
RSW Engineering
29,762,232.50————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 61–70 of 218 projects · page 7/22