DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 15 awarded projects

2026-11-04
19:00:45Live2026-11-04
0 / 15Advance Pendingpending advance projects / total projects
0 / 15IPC Pendingpending IPC projects / total projects
0 / 15Advance Paidadvance paid projects / total projects
0 / 15IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Gampaha · District

579Projects23,829.3Contract Mn
Gampaha 15 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn145.02.76% of contract42.3——————0.0%0.0%
Tender Below 50Mn9145.314.910% of contract130.4——————33.3%0.0%
DL Stage 01349.731.864% of contract17.8——————100.0%0.0%
DL Stage 0200.0——————————
DL Stage 03112.19.478% of contract2.6——————0.0%0.0%
DL Stage 04126.912.647% of contract14.4——————0.0%0.0%
PIU00.0——————————
Gampaha15279.071.526% of contract207.5000.0000.040.0%0.0%
Tender Above 50Mn1 project45.0Mn
6% paid2.7 Mn
Pending42.3Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn9 projects145.3Mn
10% paid14.9 Mn
Pending130.4Mn
Planned Fin33.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 013 projects49.7Mn
64% paid31.8 Mn
Pending17.8Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 020 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 031 project12.1Mn
78% paid9.4 Mn
Pending2.6Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 041 project26.9Mn
47% paid12.6 Mn
Pending14.4Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Gampaha15 projects279.0Mn
26% paid71.5 Mn
Pending207.5Mn
Planned Fin40.0%
Actual Fin0.0%

Avg Physical Progress per Province · Gampaha

Graphs reflect current view:15 awarded · Gampaha
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 218 projects (filtered from 579)

201–210/218 (filtered from 579)
ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
201RR/RDA/03/25/12/WP/KTR
Concreting Batawala Road
Next Engineering Services (PVT) LTD
18,670,236.20————————————
202RR/RDA/03/25/16/WP/KTR
Development of carpeting of 1 km from Gane Aramba Road, Bogalla Junction to Ambe…
Asela Construction
27,990,360.00————————————
203—
Development of 0.8 km carpeting of Newfa Mawatha
Develco Engineering (PVT) LTD
6,972,603.95————————————
204RR/RDA/03/25/18/WP/KTR
Development of carpeting of the section (length 800 m) from near Minerithenna te…
Asela Construction
17,101,775.00————————————
205—
Carpeting and development of 500 meters of Moragahakanda watta Bodumaga Senasuna…
Develco Engineering (PVT) LTD
8,285,619.00————————————
206—
Development of from Lewis Stadium to Heladiva Malshalawa
Develco Engineering (PVT) LTD
15,591,781.10————————————
207RR/RDA/06/25/44
Carpeting of Muloya Main Road Section 2
—
42,312,390.95————————————
208RR/RDA/06/25/47
Carpeting of the road from Gatakula to Madanwala via Diaudagama, Kottala
—
28,020,844.83————————————
209RR/RDA/05/25/23
Manchanayake shed eka asala sita sampath waththa haraha Galketiyawa margaya
—
28,401,905.12————————————
210RR/RDA/05/25/28
Adawala Udagama Road
—
56,161,142.68————————————
Total8,978,398,226.97——————————
—Mn
0%
—Mn
0%
Showing 201–210 of 218 projects · page 21/22