DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 0 awarded projects

2026-11-06
02:28:54Live2026-11-06
0 / 0Advance Pendingpending advance projects / total projects
0 / 0IPC Pendingpending IPC projects / total projects
0 / 0Advance Paidadvance paid projects / total projects
0 / 0IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

0%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · North Western Province · Badulla · District

579Projects23,829.3Contract Mn
Badulla 18 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn138.524.163% of contract14.4——————0.0%0.0%
Tender Below 50Mn11176.2125.671% of contract50.7——————27.3%0.0%
DL Stage 014139.7102.874% of contract36.8——————100.0%0.0%
DL Stage 02226.329.3111% of contract-3.0——————0.0%0.0%
DL Stage 0300.0——————————
DL Stage 0400.0——————————
PIU00.0——————————
Badulla18380.7281.874% of contract98.9000.0000.038.9%0.0%
Tender Above 50Mn1 project38.5Mn
63% paid24.1 Mn
Pending14.4Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn11 projects176.2Mn
71% paid125.6 Mn
Pending50.7Mn
Planned Fin27.3%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 014 projects139.7Mn
74% paid102.8 Mn
Pending36.8Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 022 projects26.3Mn
111% paid29.3 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 040 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Badulla18 projects380.7Mn
74% paid281.8 Mn
Pending98.9Mn
Planned Fin38.9%
Actual Fin0.0%

Avg Physical Progress per Province · North Western Province · Badulla

No province data available

Awarded projects will appear here

Graphs reflect current view:0 awarded · North Western Province · Badulla
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

301–310/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
301RR/RDA/25/24/14/SBP/RTP
Pimbura- Peelwatta Road
SSP Engineering
15,010,646.74————————————
302RR/RDA/25/24/16/SBP/RTP
Kalawana Salgaha Yata Road
SSP Engineering
34,292,579.12————————————
303RR/RDA/24/25/21/SBP/RTP
Sudagala Grama Seva Division, From Sudagala to Tunudola Road up the mountain to …
DKS Construction
35,222,472.34————————————
304RR/RDA/24/25/25/SBP/RTP
From the point where the Bulathgama-Pallevela road starts from Rasagala Road
Sathira Construction
7,273,850.00————————————
305RR/RDA/24/25/28/SBP/RTP
From near Kalal Ella Rubber Store to Narangalla via Navinikanda Road
KEP Construction
18,880,633.26————————————
306RR/RDA/24/25/31/SBP/RTP
Development of Koratuwegoda Road from Main Road
KEP Construction
19,882,000.02————————————
307RR/RDA/24/25/32/SBP/RTP
Weligepola to Nitta Kumbura Road
Sasiri Construction
14,421,268.00————————————
308RR/RDA/24/25/34/SBP/RTP
Matuwagala Mudun Kotu Road
DKS Construction
—————————————
309RR/RDA/24/25/35/SBP/RTP
Induruwa Junction to Kadawatha junction road joining Kuruwita - Siripagama road
Creates Consultant and Construction
70,340,000.00————————————
310RR/RDA/25/25/02/SBP/KGL
Elagapitiya Colany Road From Debathgama Pallebage to Tea Shakthi Praja Shalawa
EHL Constructions
36,210,751.61————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 301–310 of 579 projects · page 31/58