Financial Dashboard
213,999,600.01
Contract Amount (LKR)
45,277,883.86
Advance Paid (LKR incl. VAT)
—
IPCs Paid (LKR incl. VAT)
45.28 Mn
Financial Progress (21.2%)
214.00 Mn
Total Contract
45.28 Mn
Advance Paid (incl. VAT)
— Mn
IPCs Paid (incl. VAT)
45.28 Mn
Total Paid (incl. VAT)
— Mn
Advance Pend (VAT)
— Mn
IPCs Pend (VAT)
21.2%
Financial Progress
56.3%
Planned Financial Progress
Thawalanthenna Thalawakelle Road (B412)
NuwaraEliya NuwaraEliya Nuwara Eliya EE
Financial Waterfall — RDA/DRP/CEN/NUE/NUE/68 (LKR Mn)
Advance + IPCs Paid + Pending + Remaining = Contract Amount
Financial Progress
21.2% actual45.28 Mn
Total Paid
— Mn
Pending
Planned vs Actual
56.3% planned56.3%
Planned
21.2%
Actual
Financial Summary
Advance payments, IPCs & expenditure per awarded project
214.0 Mn
Total Contract
45.3 Mn
Total Paid (incl. VAT)
0.0 Mn
Pending Payments
21.2% / planned 56.3%
Financial Progress (Paid / Contract)
| Contract No | Contract (LKR) |
Advance Paid (excl. VAT) |
Advance Paid (incl. VAT) |
Advance Pend (excl. VAT) |
Advance Pend (incl. VAT) |
IPCs Paid (excl. VAT) |
IPCs Paid (incl. VAT) |
IPCs Pend (excl. VAT) |
IPCs Pend (incl. VAT) |
Overall Expenditure (excl. VAT) |
Pending Payments (excl. VAT) |
Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| RDA/DRP/CEN/NUE/NUE/68 | 213,999,600.01 | 38,371,088.02 | 45,277,883.86 | — | — | — | — | — | — | 38,371,088.02 | — |
45.28Mn
Watch
21.2%
|
45.28Mn
21.2%
|