Ditwah(CP) Project #68
Contract No.

RDA/DRP/CEN/NUE/NUE/68

Thawalanthenna Thalawakelle Road (B412)

Rehabilitation / Improvement of Thawalanthenna Thalawakelle Road (0+000 - 8+000) & (10+000 - 33+200)

Last updated: 2026-09-06 10:32

NuwaraEliya NuwaraEliya Thawalanthenna Thalawakelle Road (B412) Awarded Progress 27%
Original Contract Amount

213,999,600.01

Total Certified to Date

45,277,883.86

Overall Progress
27%

Planned: 78.1%

Planned

78.1%

Actual

27%

Presentage

-51.1%

Time Elapsed

70.3%

Days Left

53

Location & Package
ProvinceCentral Province
DistrictNuwaraEliya
EE DivisionNuwaraEliya
Package No.9
Tender ByRM&M
Scope
Road NameThawalanthenna Thalawakelle Road (B412)
Contract DescriptionRehabilitation / Improvement of Thawalanthenna Thalawakelle Road (0+000 - 8+000) & (10+000 - 33+200)
Estimated Road Lengths— km
Number of Roads0
Number of Structures
Chainage0+000 - 8+000 & 10+000 - 33+200
Scope SummaryAsphalt overlay, Retaining wall Construction, U Drain Construction & Culvert Construction
Contractor & Award
Contract No.RDA/DRP/CEN/NUE/NUE/68
S/N68
Serial No.37
Tender Batch No.4
Contractor NameGreen Scene Construction (Pvt) Ltd
ConsultantNuwara Eliya EE
Tender StatusAwarded
LOA Date2026-03-24
Contract Amount213,999,600.01
Estimate Amount296,813,201.99
Duration (Days)182
CategoryEmergency Projects