Financial Dashboard
Financial Dashboard
2026-09-07
266,607,902.15
Contract Amount (LKR)
54,694,803.46
Advance Paid (LKR incl. VAT)
—
IPCs Paid (LKR incl. VAT)
54.69 Mn
Financial Progress (20.5%)
266.6Mn
266.61 Mn
Total Contract
54.7Mn
54.69 Mn
Advance Paid (incl. VAT)
0.0Mn
— Mn
IPCs Paid (incl. VAT)
54.7Mn
54.69 Mn
Total Paid (incl. VAT)
0.0Mn
— Mn
Advance Pend (VAT)
0.0Mn
— Mn
IPCs Pend (VAT)
Overall
20.5%
Financial Progress
Planned
56.3%
Planned Financial Progress
Single Project
RDA/DRP/CEN/MTL/MTL/35
Matale
Rattota Gammaduwa Road B 392
Matale Matale Matale EE
Financial Waterfall — RDA/DRP/CEN/MTL/MTL/35 (LKR Mn)
Advance + IPCs Paid + Pending + Remaining = Contract Amount
Financial Progress
20.5% actual20.5%Actual
54.69 Mn
Total Paid
— Mn
Pending
Planned vs Actual
56.3% planned56.3%
Planned
20.5%
Actual
-35.8% behind
Financial Summary
Advance payments, IPCs & expenditure per awarded project
1 projects
Export XLSX
266.6 Mn
Total Contract
54.7 Mn
Total Paid (incl. VAT)
0.0 Mn
Pending Payments
20.5% / planned 56.3%
Financial Progress (Paid / Contract)
| Contract No | Contract (LKR) |
Advance Paid (excl. VAT) |
Advance Paid (incl. VAT) |
Advance Pend (excl. VAT) |
Advance Pend (incl. VAT) |
IPCs Paid (excl. VAT) |
IPCs Paid (incl. VAT) |
IPCs Pend (excl. VAT) |
IPCs Pend (incl. VAT) |
Overall Expenditure (excl. VAT) |
Pending Payments (excl. VAT) |
Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| RDA/DRP/CEN/MTL/MTL/35 | 266,607,902.15 | 46,351,528.36 | 54,694,803.46 | — | — | — | — | — | — | 46,351,528.36 | — |
54.69Mn
Watch
20.5%
|
54.69Mn
20.5%
|