Ditwah(CP) Financial Dashboard

Financial Dashboard

2026-09-07

213,999,600.01

Contract Amount (LKR)

45,277,883.86

Advance Paid (LKR incl. VAT)

IPCs Paid (LKR incl. VAT)

45.28 Mn

Financial Progress (21.2%)

214.0Mn

214.00 Mn

Total Contract

45.3Mn

45.28 Mn

Advance Paid (incl. VAT)

0.0Mn

Mn

IPCs Paid (incl. VAT)

45.3Mn

45.28 Mn

Total Paid (incl. VAT)

0.0Mn

Mn

Advance Pend (VAT)

0.0Mn

Mn

IPCs Pend (VAT)

Overall

21.2%

Financial Progress

Planned

56.3%

Planned Financial Progress

Single Project RDA/DRP/CEN/NUE/NUE/68

Thawalanthenna Thalawakelle Road (B412)

NuwaraEliya NuwaraEliya Nuwara Eliya EE

Financial Waterfall — RDA/DRP/CEN/NUE/NUE/68 (LKR Mn)

Advance + IPCs Paid + Pending + Remaining = Contract Amount

Financial Progress
21.2% actual
21.2%Actual

45.28 Mn

Total Paid

Mn

Pending

Planned vs Actual
56.3% planned

56.3%

Planned

21.2%

Actual

-35.1% behind
Financial Summary

Advance payments, IPCs & expenditure per awarded project

1 projects Export XLSX

214.0 Mn

Total Contract

45.3 Mn

Total Paid (incl. VAT)

0.0 Mn

Pending Payments

21.2% / planned 56.3%

Financial Progress (Paid / Contract)

Contract No Contract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial Progress Financial Progress
with Outstanding
RDA/DRP/CEN/NUE/NUE/68 213,999,600.01 38,371,088.02 45,277,883.86 38,371,088.02
45.28Mn
21.2%
Watch
45.28Mn
21.2%