DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 5 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-04 12:46Live
Graphs reflect current view:5 awarded · North Western Province · EE: Kurunegala
100% awarded
0
Awarded
5 total projects in portfolio
Awarded projects5
RDA/DRP/NWP/KURU/KULI/01RRDA/DRP/NWP/KURU/KURU/02RRDA/DRP/NWP/KURU/KURU/03RRDA/DRP/NWP/KURU/KURU/04RDA/DRP/NWP/KURU/MAHO/05
Click to filter the awarded table
768.2M
768.2 Mn
Contract Value
Awarded projects5
RDA/DRP/NWP/KURU/KULI/01RRDA/DRP/NWP/KURU/KURU/02RRDA/DRP/NWP/KURU/KURU/03RRDA/DRP/NWP/KURU/KURU/04RDA/DRP/NWP/KURU/MAHO/05
Click to filter the awarded table
Avg
28.8%
3
works in progress
0 completed
Avg Progress
Awarded projects5
RDA/DRP/NWP/KURU/KULI/01RRDA/DRP/NWP/KURU/KURU/02RRDA/DRP/NWP/KURU/KURU/03RRDA/DRP/NWP/KURU/KURU/04RDA/DRP/NWP/KURU/MAHO/05
Click to filter the awarded table
64.8M
64.8 Mn
Total Expenditure (incl. VAT)
Awarded projects5
RDA/DRP/NWP/KURU/KULI/01RRDA/DRP/NWP/KURU/KURU/02RRDA/DRP/NWP/KURU/KURU/03RRDA/DRP/NWP/KURU/KURU/04RDA/DRP/NWP/KURU/MAHO/05
Click to filter the awarded table
0%
0
On Progress
0 / 5 awarded
On Progress (incl. completed)0
No projects
Click to filter the awarded table
0%
0
Delay
0 / 5 awarded
Delay0
No projects
Click to filter the awarded table
100%
0
Critical Delay
5 / 5 awarded
Critical Delay5
RDA/DRP/NWP/KURU/KULI/01RRDA/DRP/NWP/KURU/KURU/02RRDA/DRP/NWP/KURU/KURU/03RRDA/DRP/NWP/KURU/KURU/04RDA/DRP/NWP/KURU/MAHO/05
Click to filter the awarded table
0%
0
Completed
0 / 5 awarded
Completed0
No projects
Click to filter the awarded table
Portfolio Breakdown · North Western Province · EE: Kurunegala · EE Office
Avg Physical Progress per EE Division · North Western Province · EE: Kurunegala
At-Risk Projects · North Western Province · EE: Kurunegala
- RDA/DRP/NWP/KURU/KURU/04Rehabilitation / Improvement of Muththettugala Hiripitiya Road (B300) (10+880 - 11+080) & Vilakatupotha Ganewatta Kumbukgete road (B478) (9+100 - 9+400)Delay105 Days in Delay · 62%
- RDA/DRP/NWP/KURU/MAHO/05Rehabilitation / Improvement of Galgamuwa - Nikawewa Road (B126) (6+000-20+000), Danikithawa - Ambanpola Road (B089) (20+925 - 21+000), Nikaweratiya - Moragollagama - Siyambalangamuwa Road (B326) (40+760 - 48+240), Malsiripura - Rambe Road (B610) (7+500 - 9+650), Ibbagamuwa - Kumbukgate - Madagalla Road (B159) (16+450 - 28+680), Hiripitiya - Galtenwewa Road (B609) (9+580-9+680), Padeniya - Anuradapura Road (AA028) (8+480-8+800) and Katugasthota - Kurunegala - Puththalama Road (AA010) (73+745-73 -870) in Maho EE DivisionDelay64 Days in Delay · 70%
Portfolio Timeline· 5 scheduled projects · North Western Province · EE: Kurunegala Toggle
2026-04-21 today2027-03-29
Portfolio · Awarded Works
Awarded Projects
5 projects
Filter awarded works
5 matching projects1 active
| Contract No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|
| RDA/DRP/NWP/KURU/KULI/01R | Rehabilitation / Improvement of Selected Sections on Pannala Kuliyapitiya Road (B356) (0+000-6+000), Dandagamuwa Udawela Road (B088) (4+000 - 6+000), Marawila Udubaddawa Road (B272) (11+000 - 12+000), Kurunegala Narammala Madampe Road (B247) (52+000 - 54+000), Narammala Dankotuwa Road (B308) (16+000-37+000) and Alawwa Maharagama Road (B009) (1+000 - 14+200) in Kuliyapitiya EE Division | 12% | 181,456,551.09 | — | Awarded |
| RDA/DRP/NWP/KURU/KURU/02R | Rehabilitation / Improvement and Structure Improvement of Mallawapitiya Rambodagalla Keppitigala Road (30+943 - 33+858), Katugasthota Kurunegala Puttalam Road (AA010) (30+000 - 34+600) and Mawathagama Muwankanda Road (B281) (0+000 - 7+000) | 0% | 208,660,417.21 | 192,045,728.78 | Awarded |
| RDA/DRP/NWP/KURU/KURU/03R | Rehabilitation / Improvement of Thalgodapitiya Yatawaththa Road (B409) (9+100 - 14+650) | 0% | 129,109,243.85 | 117,113,346.84 | Awarded |
| RDA/DRP/NWP/KURU/KURU/04 | Rehabilitation / Improvement of Muththettugala Hiripitiya Road (B300) (10+880 - 11+080) & Vilakatupotha Ganewatta Kumbukgete road (B478) (9+100 - 9+400) | 62% | 97,503,423.17 | 105,193,927.73 | Awarded |
| RDA/DRP/NWP/KURU/MAHO/05 | Rehabilitation / Improvement of Galgamuwa - Nikawewa Road (B126) (6+000-20+000), Danikithawa - Ambanpola Road (B089) (20+925 - 21+000), Nikaweratiya - Moragollagama - Siyambalangamuwa Road (B326) (40+760 - 48+240), Malsiripura - Rambe Road (B610) (7+500 - 9+650), Ibbagamuwa - Kumbukgate - Madagalla Road (B159) (16+450 - 28+680), Hiripitiya - Galtenwewa Road (B609) (9+580-9+680), Padeniya - Anuradapura Road (AA028) (8+480-8+800) and Katugasthota - Kurunegala - Puththalama Road (AA010) (73+745-73 -870) in Maho EE Division | 70% | 151,515,024.36 | 166,163,663.09 | Awarded |
Showing 1–5 of 5
Source: DRRRP • 5 projects • Data updated 2026-11-04 12:46 • 14:29:27 System live • Sri Lanka • 1 districts