DRRRP · Sri Lanka
Project Monitoring Dashboard
Comprehensive overview of 5 infrastructure projects
under the Disaster Rebuild and Rural Road Project — Sri Lanka.
Updated 2026-11-04 12:46Live
Graphs reflect current view:5 awarded · Polonnaruwa
100% awarded
0
Awarded
5 total projects in portfolio
Awarded projects5
RDA/DRP/NCP/POL/POL/09RDA/DRP/NCP/POL/HAB/04RDA/DRP/NCP/POL/POL/08RDA/DRP/NCP/POL/POL/10RDA/DRP/NCP/POL/POL/11
Click to filter the awarded table
235.4M
235.4 Mn
Contract Value
Awarded projects5
RDA/DRP/NCP/POL/POL/09RDA/DRP/NCP/POL/HAB/04RDA/DRP/NCP/POL/POL/08RDA/DRP/NCP/POL/POL/10RDA/DRP/NCP/POL/POL/11
Click to filter the awarded table
Avg
68.2%
4
works in progress
1 completed
Avg Progress
Awarded projects5
RDA/DRP/NCP/POL/POL/09RDA/DRP/NCP/POL/HAB/04RDA/DRP/NCP/POL/POL/08RDA/DRP/NCP/POL/POL/10RDA/DRP/NCP/POL/POL/11
Click to filter the awarded table
64.7M
64.7 Mn
Total Expenditure (incl. VAT)
Awarded projects5
RDA/DRP/NCP/POL/POL/09RDA/DRP/NCP/POL/HAB/04RDA/DRP/NCP/POL/POL/08RDA/DRP/NCP/POL/POL/10RDA/DRP/NCP/POL/POL/11
Click to filter the awarded table
60%
0
Critical Delay
3 / 5 awarded
Critical Delay3
Click to filter the awarded table
Portfolio Breakdown · Polonnaruwa · District
Avg Physical Progress per EE Division · Polonnaruwa
At-Risk Projects · Polonnaruwa
- RDA/DRP/NCP/POL/POL/10Rehabilitation / Improvement and Construction of New Drainage At 65-78km on Maradankadawala Habarana Thirikkondiyadumadu Road (A011)RoadDelay299 Days in Delay · 55%
- RDA/DRP/NCP/POL/HAB/04Rehabilitation / Improvement of washed out section between 30/1 & 30/2 Bridges on Dambulla - Bakamoona - Kalagahawela Road (B-615) & at 27/5 Bridge (26+500-27+000) on Naula - Elahera - Pallegama -Hettipola Road (B-312)Delay299 Days in Delay · 90%
- RDA/DRP/NCP/POL/POL/09Rehabilitation / Improvement and Reconstruction of Culvert No. 104/2, Construction of New Drainage At 83km, and Concrete Hard Shoulder at 83 Km on Maradankadawala - Habarana - Thirikkondiyadumadu Road (A-11) (82+110 - 82+860 (B/S)Delay180 Days in Delay · 56%
- RDA/DRP/NCP/POL/POL/11Rehabilitation / Improvement and Construction of New Drainage on Polonnaruwa-Thambala -Sungawila -Somawathiya- RoadDelay54 Days in Delay · 40%
Portfolio Timeline· 5 scheduled projects · Polonnaruwa Toggle
2026-02-06 today2026-11-04
Portfolio · Awarded Works
Awarded Projects
3 projects
Filter awarded works
3 matching projects1 active
| Contract No. | Contract Name | Progress | LOA Amount | Estimate Amount | Status |
|---|---|---|---|---|---|
| RDA/DRP/NCP/POL/POL/09 | Rehabilitation / Improvement and Reconstruction of Culvert No. 104/2, Construction of New Drainage At 83km, and Concrete Hard Shoulder at 83 Km on Maradankadawala - Habarana - Thirikkondiyadumadu Road (A-11) (82+110 - 82+860 (B/S) | 56% | 94,457,054.66 | 119,605,688.26 | Awarded |
| RDA/DRP/NCP/POL/POL/10 | Rehabilitation / Improvement and Construction of New Drainage At 65-78km on Maradankadawala Habarana Thirikkondiyadumadu Road (A011)Road | 55% | 29,767,050.53 | 33,973,362.07 | Awarded |
| RDA/DRP/NCP/POL/POL/11 | Rehabilitation / Improvement and Construction of New Drainage on Polonnaruwa-Thambala -Sungawila -Somawathiya- Road | 40% | 44,474,738.82 | 57,461,708.21 | Awarded |
Showing 1–3 of 3
Source: DRRRP • 5 projects • Data updated 2026-11-04 12:46 • 13:38:22 System live • Sri Lanka • 1 districts