DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 7 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-04 16:23Live
Graphs reflect current view:7 awarded · EE: Norwood

Portfolio Breakdown · EE: Norwood · EE Office

155Awarded237Total
Norwood 7 awarded of 21 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Emergency330100%435.8369.1348.234.09% of contract96.0%45.7%
DC - Roads62433%3,625.0979.214.457.86% of contract1.8%14.0%
DC - Slope82625%3,206.1484.8——0.0%0.0%
PD(CP) - Slope4040%102.30.0————
Norwood2171433%7,369.21,833.0362.691.85% of contract41.7%23.6%

Avg Physical Progress per EE Division · EE: Norwood

Portfolio Timeline· 5 scheduled projects · EE: Norwood Toggle
Portfolio · Awarded Works

Awarded Projects

3 projects

3/3 (filtered)

Filter awarded works

3 matching projects1 active

ActiveCritical Delay
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/NUE/NUR/97
Rehabilitation/Improvement of Nawalapitiya Ginigathena Road (B-319)(7+200-12+200)
62%
93,758,217.76104,490,700.33Awarded
RDA/DRP/CEN/NUE/NUR/98
Rehabilitation/Improvement Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Hrangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)
44%
188,617,394.68222,691,835.72Awarded
RDA/DRP/CEN/NUE/NUR/101
Rehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970)
31%
86,746,198.17108,611,538.67Awarded
Showing 1–3 of 3
Per page:
Source: DRRRP • 21 projects • Data updated 2026-11-04 16:23 • 17:24:49