Pending207.2Mn
Planned Fin85.3%
Actual Fin15.3%
Advance & IPC
Advance paid83 proj · 2,738.9 Mn
IPC paid62 proj · 1,049.9 Mn

Monitor financial performance across 11 awarded projects
846.20 Mn
Total Contract
101.22 Mn
Advance Paid (excl. VAT)
32.85 Mn
IPCs Paid (excl. VAT)
134.07 Mn
Total Paid (excl. VAT)
158.20 Mn
Total Paid (incl. VAT)
— Mn
Advance Pend (incl. VAT)
— Mn
IPCs Pend (incl. VAT)
158.20 Mn
Total (Paid+Pend) (incl. VAT)
Paid incl + Adv Pend incl + IPC Pend incl
15.8%
Financial Progress (excl. VAT)
Total (Paid+Pend) excl / Contract
97.9%
Planned Financial Progress
Planned share of contract value
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 144 | 24,785.9 | 4,470.518% of contract | 207.2 | 86 | 83 | 2,738.9 | 125 | 62 | 1,049.9 | 85.3% | 15.3% |
| DC - Roads | 9 | 5,783.2 | — | — | — | — | — | — | — | — | 0.4% | 0.0% |
| DC - Slope | 10 | 3,258.5 | — | — | — | — | — | — | — | — | 0.3% | 0.0% |
| PD(CP) - Slope | 8 | 177.7 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| All Provinces | 171 | 34,005.3 | 4,470.513% of contract | 207.2 | 86 | 83 | 2,738.9 | 125 | 62 | 1,049.9 | 71.9% | 11.1% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 31 | 4,646.7 | 969.921% of contract | 73.6 | 19 | 19 | 566.4 | 32 | 13 | 255.6 | 74.4% | 17.7% |
| DC - Roads | 8 | 5,116.6 | — | — | — | — | — | — | — | — | 0.5% | 0.0% |
| DC - Slope | 10 | 3,258.5 | — | — | — | — | — | — | — | — | 0.3% | 0.0% |
| PD(CP) - Slope | 8 | 177.7 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| Central Province | 57 | 13,199.5 | 969.97% of contract | 73.6 | 19 | 19 | 566.4 | 32 | 13 | 255.6 | 40.6% | 6.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 32 | 7,417.7 | 1,441.219% of contract | — | 22 | 22 | 854.4 | 48 | 19 | 367.2 | 92.2% | 16.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Sabaragamuwa Province | 32 | 7,417.7 | 1,441.219% of contract | 0.0 | 22 | 22 | 854.4 | 48 | 19 | 367.2 | 92.2% | 16.5% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 25 | 5,571.5 | 1,201.222% of contract | — | 20 | 20 | 804.9 | 23 | 15 | 213.0 | 89.7% | 18.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Uva Province | 25 | 5,571.5 | 1,201.222% of contract | 0.0 | 20 | 20 | 804.9 | 23 | 15 | 213.0 | 89.7% | 18.3% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 16 | 2,880.4 | 449.216% of contract | — | 11 | 11 | 324.6 | 10 | 6 | 56.1 | 100.0% | 13.2% |
| DC - Roads | 1 | 666.6 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Western Province | 17 | 3,547.0 | 449.213% of contract | 0.0 | 11 | 11 | 324.6 | 10 | 6 | 56.1 | 94.1% | 10.7% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 12 | 1,941.6 | 155.28% of contract | 133.6 | 6 | 3 | 66.8 | 5 | 3 | 64.7 | 70.4% | 6.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| North Western Province | 12 | 1,941.6 | 155.28% of contract | 133.6 | 6 | 3 | 66.8 | 5 | 3 | 64.7 | 70.4% | 6.8% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 9 | 852.8 | 95.511% of contract | — | 2 | 2 | 20.5 | 3 | 2 | 60.5 | 86.6% | 9.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Eastern Province | 9 | 852.8 | 95.511% of contract | 0.0 | 2 | 2 | 20.5 | 3 | 2 | 60.5 | 86.6% | 9.5% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 11 | 846.2 | 158.219% of contract | — | 6 | 6 | 101.2 | 4 | 4 | 32.8 | 98.2% | 15.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| North Central Province | 11 | 846.2 | 158.219% of contract | 0.0 | 6 | 6 | 101.2 | 4 | 4 | 32.8 | 98.2% | 15.8% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 600.5 | — | — | — | — | — | — | — | — | 46.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Northern Province | 6 | 600.5 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 46.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 28.4 | — | — | — | — | — | — | — | — | 100.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Southern Province | 2 | 28.4 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 100.0% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 144 | 24,785.9 | 4,470.518% of contract | 207.2 | 86 | 83 | 2,738.9 | 125 | 62 | 1,049.9 | 85.3% | 15.3% |
| DC - Roads | 9 | 5,783.2 | — | — | — | — | — | — | — | — | 0.4% | 0.0% |
| DC - Slope | 10 | 3,258.5 | — | — | — | — | — | — | — | — | 0.3% | 0.0% |
| PD(CP) - Slope | 8 | 177.7 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| All Districts | 171 | 34,005.3 | 4,470.513% of contract | 207.2 | 86 | 83 | 2,738.9 | 125 | 62 | 1,049.9 | 71.9% | 11.1% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 12 | 1,520.3 | 329.622% of contract | 33.9 | 6 | 6 | 184.4 | 13 | 5 | 95.0 | 62.3% | 18.4% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 3 | 1,154.7 | — | — | — | — | — | — | — | — | 0.9% | 0.0% |
| PD(CP) - Slope | 8 | 177.7 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| Kandy | 23 | 2,852.8 | 329.612% of contract | 33.9 | 6 | 6 | 184.4 | 13 | 5 | 95.0 | 32.6% | 9.8% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 9 | 1,458.1 | 292.420% of contract | 20.2 | 6 | 6 | 187.7 | 8 | 4 | 60.1 | 73.9% | 17.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 372.1 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Matale | 10 | 1,830.2 | 292.416% of contract | 20.2 | 6 | 6 | 187.7 | 8 | 4 | 60.1 | 66.5% | 13.5% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 10 | 1,668.3 | 347.921% of contract | 19.5 | 7 | 7 | 194.3 | 11 | 4 | 100.5 | 89.4% | 17.7% |
| DC - Roads | 8 | 5,116.6 | — | — | — | — | — | — | — | — | 0.5% | 0.0% |
| DC - Slope | 6 | 1,731.6 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nuwara Eliya | 24 | 8,516.5 | 347.94% of contract | 19.5 | 7 | 7 | 194.3 | 11 | 4 | 100.5 | 37.4% | 3.5% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 395.9 | 24.26% of contract | — | 2 | 2 | 20.5 | — | — | — | 94.8% | 5.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Ampara | 3 | 395.9 | 24.26% of contract | 0.0 | 2 | 2 | 20.5 | 0 | 0 | 0.0 | 94.8% | 5.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 113.1 | 53.447% of contract | — | — | — | — | 2 | 1 | 45.3 | 100.0% | 40.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Batticaloa | 1 | 113.1 | 53.447% of contract | 0.0 | 0 | 0 | 0.0 | 2 | 1 | 45.3 | 100.0% | 40.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 343.9 | 17.95% of contract | — | — | — | — | 1 | 1 | 15.2 | 79.1% | 4.4% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Trincomalee | 5 | 343.9 | 17.95% of contract | 0.0 | 0 | 0 | 0.0 | 1 | 1 | 15.2 | 79.1% | 4.4% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 610.8 | 93.515% of contract | — | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Anuradhapura | 6 | 610.8 | 93.515% of contract | 0.0 | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 235.4 | 64.727% of contract | — | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Polonnaruwa | 5 | 235.4 | 64.727% of contract | 0.0 | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 843.3 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 65.1% | 6.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kurunegala | 6 | 843.3 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 65.1% | 6.5% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Puttalam | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 359.7 | — | — | — | — | — | — | — | — | 2.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Jaffna | 2 | 359.7 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 2.2% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 62.2 | — | — | — | — | — | — | — | — | 68.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kilinochchi | 1 | 62.2 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 68.2% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 98.5 | — | — | — | — | — | — | — | — | 62.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Mannar | 1 | 98.5 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 62.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 37.3 | — | — | — | — | — | — | — | — | 81.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Mullaitivu | 1 | 37.3 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 81.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 42.8 | — | — | — | — | — | — | — | — | 62.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Vavuniya | 1 | 42.8 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 62.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 10 | 2,440.9 | 548.422% of contract | — | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kegalle | 10 | 2,440.9 | 548.422% of contract | 0.0 | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 22 | 4,976.9 | 892.818% of contract | — | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Ratnapura | 22 | 4,976.9 | 892.818% of contract | 0.0 | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 28.4 | — | — | — | — | — | — | — | — | 100.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Galle | 2 | 28.4 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 100.0% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 23 | 5,411.1 | 1,142.021% of contract | — | 18 | 18 | 776.9 | 19 | 13 | 190.9 | 88.8% | 17.9% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Badulla | 23 | 5,411.1 | 1,142.021% of contract | 0.0 | 18 | 18 | 776.9 | 19 | 13 | 190.9 | 88.8% | 17.9% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 160.3 | 59.237% of contract | — | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Monaragala | 2 | 160.3 | 59.237% of contract | 0.0 | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,433.0 | 196.214% of contract | — | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Colombo | 8 | 1,433.0 | 196.214% of contract | 0.0 | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,447.4 | 253.117% of contract | — | 6 | 6 | 214.5 | — | — | — | 100.0% | 14.8% |
| DC - Roads | 1 | 666.6 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Gampaha | 9 | 2,114.0 | 253.112% of contract | 0.0 | 6 | 6 | 214.5 | 0 | 0 | 0.0 | 88.9% | 10.1% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 31 | 4,646.7 | 969.921% of contract | 73.6 | 19 | 19 | 566.4 | 32 | 13 | 255.6 | 74.4% | 17.7% |
| DC - Roads | 8 | 5,116.6 | — | — | — | — | — | — | — | — | 0.5% | 0.0% |
| DC - Slope | 5 | 1,984.7 | — | — | — | — | — | — | — | — | 0.5% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| All Consultants | 44 | 11,748.0 | 969.98% of contract | 73.6 | 19 | 19 | 566.4 | 32 | 13 | 255.6 | 52.6% | 7.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 15 | 2,082.2 | 381.018% of contract | 43.8 | 7 | 7 | 213.4 | 15 | 6 | 109.6 | 61.9% | 15.5% |
| DC - Roads | 6 | 4,137.5 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Slope | 5 | 1,984.7 | — | — | — | — | — | — | — | — | 0.5% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Team Leader | 26 | 8,204.4 | 381.05% of contract | 43.8 | 7 | 7 | 213.4 | 15 | 6 | 109.6 | 35.8% | 3.9% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 369.1 | 34.09% of contract | — | 2 | 2 | 28.9 | — | — | — | 96.0% | 7.8% |
| DC - Roads | 2 | 979.2 | — | — | — | — | — | — | — | — | 1.8% | 0.0% |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Norwood EE | 5 | 1,348.3 | 34.03% of contract | 0.0 | 2 | 2 | 28.9 | 0 | 0 | 0.0 | 58.3% | 2.1% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 1,281.7 | 272.221% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 76.3% | 18.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Matale EE | 5 | 1,281.7 | 272.221% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 76.3% | 18.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 4 | 753.2 | 253.234% of contract | 9.7 | 3 | 3 | 128.7 | 9 | 3 | 85.9 | 100.0% | 28.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nuwara Eliya EE | 4 | 753.2 | 253.234% of contract | 9.7 | 3 | 3 | 128.7 | 9 | 3 | 85.9 | 100.0% | 28.5% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nalanda EE | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 47.8 | 9.219% of contract | — | 1 | 1 | 7.8 | — | — | — | 100.0% | 16.4% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Hanguranketha EE | 1 | 47.8 | 9.219% of contract | 0.0 | 1 | 1 | 7.8 | 0 | 0 | 0.0 | 100.0% | 16.4% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 129 | 22,610.7 | 4,184.219% of contract | 207.2 | 81 | 78 | 2,556.7 | 122 | 60 | 989.5 | 85.7% | 15.7% |
| DC - Roads | 8 | 5,116.6 | — | — | — | — | — | — | — | — | 0.5% | 0.0% |
| DC - Slope | 10 | 3,258.5 | — | — | — | — | — | — | — | — | 0.3% | 0.0% |
| PD(CP) - Slope | 8 | 177.7 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| All EE Offices | 155 | 31,163.5 | 4,184.213% of contract | 207.2 | 81 | 78 | 2,556.7 | 122 | 60 | 989.5 | 71.4% | 11.4% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,251.4 | 304.624% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 84.3% | 20.6% |
| DC - Roads | 6 | 4,137.5 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Slope | 2 | 734.6 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nuwara Eliya | 14 | 6,123.4 | 304.65% of contract | 19.5 | 4 | 4 | 157.6 | 11 | 4 | 100.5 | 36.1% | 4.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 22 | 4,976.9 | 892.818% of contract | — | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Ratnapura | 22 | 4,976.9 | 892.818% of contract | 0.0 | 14 | 14 | 521.2 | 30 | 11 | 235.4 | 95.7% | 15.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 19 | 4,275.2 | 951.322% of contract | — | 15 | 15 | 615.2 | 19 | 13 | 190.9 | 92.4% | 18.9% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Badulla | 19 | 4,275.2 | 951.322% of contract | 0.0 | 15 | 15 | 615.2 | 19 | 13 | 190.9 | 92.4% | 18.9% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 10 | 2,440.9 | 548.422% of contract | — | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kegalle | 10 | 2,440.9 | 548.422% of contract | 0.0 | 8 | 8 | 333.2 | 18 | 8 | 131.7 | 84.5% | 19.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 369.1 | 34.09% of contract | — | 2 | 2 | 28.9 | — | — | — | 96.0% | 7.8% |
| DC - Roads | 2 | 979.2 | — | — | — | — | — | — | — | — | 1.8% | 0.0% |
| DC - Slope | 2 | 484.8 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Norwood | 7 | 1,833.0 | 34.02% of contract | 0.0 | 2 | 2 | 28.9 | 0 | 0 | 0.0 | 41.7% | 1.6% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,105.1 | 271.425% of contract | 33.9 | 5 | 5 | 151.1 | 9 | 4 | 79.0 | 73.7% | 20.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 628.9 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 3 | 57.8 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| Kundasale | 12 | 1,791.8 | 271.415% of contract | 33.9 | 5 | 5 | 151.1 | 9 | 4 | 79.0 | 49.1% | 12.8% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,345.4 | 272.220% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 76.2% | 17.1% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 372.1 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Matale | 7 | 1,717.6 | 272.216% of contract | 17.2 | 4 | 4 | 177.7 | 5 | 2 | 52.9 | 65.3% | 13.4% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,447.4 | 253.117% of contract | — | 6 | 6 | 214.5 | — | — | — | 100.0% | 14.8% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Gampaha | 8 | 1,447.4 | 253.117% of contract | 0.0 | 6 | 6 | 214.5 | 0 | 0 | 0.0 | 100.0% | 14.8% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 8 | 1,433.0 | 196.214% of contract | — | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Colombo | 8 | 1,433.0 | 196.214% of contract | 0.0 | 5 | 5 | 110.1 | 10 | 6 | 56.1 | 100.0% | 11.6% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Chilaw | 6 | 1,098.3 | 90.48% of contract | 94.7 | 3 | 1 | 23.2 | 2 | 2 | 53.4 | 75.6% | 7.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 768.2 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 72.5% | 7.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kurunegala | 5 | 768.2 | 64.88% of contract | 38.9 | 3 | 2 | 43.6 | 3 | 1 | 11.4 | 72.5% | 7.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 6 | 610.8 | 93.515% of contract | — | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Anuradhapura | 6 | 610.8 | 93.515% of contract | 0.0 | 3 | 3 | 73.1 | 1 | 1 | 6.2 | 96.7% | 13.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 47.8 | 9.219% of contract | — | 1 | 1 | 7.8 | — | — | — | 100.0% | 16.4% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 2 | 512.3 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Hanguranketha | 3 | 560.1 | 9.22% of contract | 0.0 | 1 | 1 | 7.8 | 0 | 0 | 0.0 | 33.3% | 1.4% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 386.7 | — | — | — | — | — | — | — | — | 2.7% | 0.0% |
| PD(CP) - Slope | 4 | 93.8 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| Gampola | 5 | 480.5 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 0.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 359.7 | — | — | — | — | — | — | — | — | 2.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Jaffna | 2 | 359.7 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 2.2% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 193.4 | 58.230% of contract | — | 1 | 1 | 33.3 | 4 | 1 | 16.0 | 100.0% | 25.5% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 1 | 139.1 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| PD(CP) - Slope | 1 | 26.1 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| Kadugannawa | 3 | 358.6 | 58.216% of contract | 0.0 | 1 | 1 | 33.3 | 4 | 1 | 16.0 | 33.3% | 13.7% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 5 | 235.4 | 64.727% of contract | — | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Polonnaruwa | 5 | 235.4 | 64.727% of contract | 0.0 | 3 | 3 | 28.1 | 3 | 3 | 26.7 | 100.0% | 23.3% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 221.8 | — | — | — | — | — | — | — | — | 19.2% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Kandy | 3 | 221.8 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 19.2% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 160.3 | 59.237% of contract | — | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Monaragala | 2 | 160.3 | 59.237% of contract | 0.0 | 2 | 2 | 28.0 | 4 | 2 | 22.1 | 100.0% | 31.3% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Nalanda | 3 | 112.6 | 20.218% of contract | 2.9 | 2 | 2 | 10.0 | 3 | 2 | 7.1 | 69.5% | 15.2% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 49.2 | — | — | — | — | — | — | — | — | 0.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Trincomalee | 1 | 49.2 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 0.0% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 42.8 | — | — | — | — | — | — | — | — | 62.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Vavuniya | 1 | 42.8 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 62.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 1 | 37.3 | — | — | — | — | — | — | — | — | 81.5% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Mullaitivu | 1 | 37.3 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 81.5% | 0.0% |
| Category | Projects | Contract LKR Mn | Paid & Pending | Advance | IPC | Planned Fin % | Actual Fin % | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Paid Mn + % | Pending Mn | Adv Req | Adv Paid | Adv Paid Mn | IPC Req | IPC Paid | IPC Paid Mn | |||||
| Emergency | 2 | 28.4 | — | — | — | — | — | — | — | — | 100.0% | 0.0% |
| DC - Roads | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| DC - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| PD(CP) - Slope | 0 | 0.0 | — | — | — | — | — | — | — | — | — | — |
| Galle | 2 | 28.4 | 0.00% of contract | 0.0 | 0 | 0 | 0.0 | 0 | 0 | 0.0 | 100.0% | 0.0% |
Advance payments, IPCs & expenditure per awarded project · 3 projects (filtered from 171)
Filter financial register
3 matching projects1 active
| S/N | Contract No | Contract Name | Contractor | Contract (LKR) | Advance Paid (excl. VAT) | Advance Paid (incl. VAT) | Advance Pend (excl. VAT) | Advance Pend (incl. VAT) | IPCs Paid (excl. VAT) | IPCs Paid (incl. VAT) | IPCs Pend (excl. VAT) | IPCs Pend (incl. VAT) | Overall Expenditure (excl. VAT) | Pending Payments (excl. VAT) | Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | RDA/DRP/SAB/RAT/PEL/19 | Rehabilitation / Improvement and Retaining wall Construction of (Galle - Deniya… | Solinro Builders | 95,082,996.58 | 16,436,817.56 | 19,395,444.72 | — | — | 38,373,715.88 | 45,280,984.74 | — | — | 54,810,533.44 | — | 64.68Mn On Track68% | 64.68Mn 68% |
| 2 | RDA/DRP/NCP/POL/POL/08 | Rehabilitation / Improvement and Reconstruction of 31/1 Culvert, Construction Of… | Sawsiri Construction | 17,459,311.37 | — | — | — | — | 9,866,233.21 | 11,642,155.19 | — | — | 9,866,233.21 | — | 11.64Mn On Track66.7% | 11.64Mn 66.7% |
| 3 | RDA/DRP/SP/GAL/GAL/02 | Rehabilitation of Gabbion Walls along Galle - Deniyaya - Madampe Road (from7+700… | Ceylon Construction Industry Development… | 8,991,852.34 | — | — | — | — | — | — | — | — | — | — | — | — |
| Total | 121,534,160.29 | 16,436,817.56 | 19,395,444.72 | — | — | 48,239,949.09 | 56,923,139.93 | — | — | 64,676,766.65 | — | 76.32Mn 62.8% | 76.32Mn 62.8% | |||