Pendingโ
Planned Fin96.9%
Actual Fin13.0%
Advance & IPC
Advance paid3 proj ยท 73.1 Mn
IPC paid1 proj ยท 6.2 Mn
Monitor financial performance across 6 awarded projects
610.84 Mn
Total Contract
73.09 Mn
Advance Paid (excl. VAT)
6.18 Mn
IPCs Paid (excl. VAT)
79.26 Mn
Total Paid (excl. VAT)
93.53 Mn
Total Paid (incl. VAT)
โ Mn
Advance Pend (incl. VAT)
โ Mn
IPCs Pend (incl. VAT)
93.53 Mn
Total (Paid+Pend) (incl. VAT)
Paid incl + Adv Pend incl + IPC Pend incl
13%
Financial Progress (excl. VAT)
Total (Paid+Pend) excl / Contract
97.3%
Planned Financial Progress
Planned share of contract value
Scroll horizontally โ 171 projects
District baseline โ overall all categories (consultant filter excluded for comparison) ยท amounts incl. VAT
Advance payments, IPCs & expenditure per awarded project ยท 171 projects
Filter financial register
171 matching projects
| S/N | Contract No | Contract Name | Contractor | Contract (LKR) | Advance Paid (excl. VAT) | Advance Paid (incl. VAT) | Advance Pend (excl. VAT) | Advance Pend (incl. VAT) | IPCs Paid (excl. VAT) | IPCs Paid (incl. VAT) | IPCs Pend (excl. VAT) | IPCs Pend (incl. VAT) | Overall Expenditure (excl. VAT) | Pending Payments (excl. VAT) | Financial Progress | Financial Progress with Outstanding |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 91 | RDA/DRP/SAB/KEG/RUW/31 | Rehabilitation of Kegalle - Bulathkohupitiya - Karawanella Road due to catastropโฆ | Tudawe Brothers (Pvt) Ltd | 269,890,586.86 | 48,845,015.80 | 57,637,118.64 | โ | โ | 8,891,636.65 | 10,492,131.25 | โ | โ | 57,736,652.45 | โ | 68.13Mn Watch25.2% | 68.13Mn 25.2% |
| 92 | RDA/DRP/WP/COL/AVI/02 | Rehabilitation / Improvement of Damage Sections on Colombo - Hanwella Low Level โฆ | Keangnam Engineering & Construction (Pvtโฆ | 279,374,027.90 | โ | โ | โ | โ | 6,828,549.84 | 8,057,688.81 | โ | โ | 6,828,549.84 | โ | 8.06Mn Behind2.9% | 8.06Mn 2.9% |
| 93 | RDA/DRP/WP/COL/AVI/03 | Rehabilitation / Improvement and Asphalt Overlaying on Colombo - Horana Road (B0โฆ | Keangnam Engineering & Construction (Pvtโฆ | 176,739,557.41 | 382,642.19 | 451,517.79 | โ | โ | 838,664.06 | 989,623.60 | โ | โ | 1,221,306.25 | โ | 1.44Mn Behind0.8% | 1.44Mn 0.8% |
| 94 | RDA/DRP/WP/COL/AVI/04 | Rehabilitation / Improvement and Asphalt Overlaying on Mampe Kottawa Road (B267)โฆ | Keangnam Engineering & Construction (Pvtโฆ | 94,697,340.01 | 17,192,698.18 | 20,287,383.86 | โ | โ | 30,212,899.20 | 35,651,221.05 | โ | โ | 47,405,597.38 | โ | 55.94Mn On Track59.1% | 55.94Mn 59.1% |
| 95 | RDA/DRP/WP/COL/AVI/05 | Rehabilitation / Improvement and Asphalt Overlaying on Panagoda Henpita Road (B3โฆ | Keangnam Engineering & Construction (Pvtโฆ | 225,228,168.18 | โ | โ | โ | โ | 1,635,814.91 | 1,930,261.59 | โ | โ | 1,635,814.91 | โ | 1.93Mn Behind0.9% | 1.93Mn 0.9% |
| 96 | RDA/DRP/NWP/KURU/KULI/01R | Rehabilitation / Improvement of Selected Sections on Pannala Kuliyapitiya Road (โฆ | Can Construction and Consultancy (Pvt) Lโฆ | 181,456,551.09 | โ | โ | 32,952,100.20 | 38,883,478.24 | โ | โ | โ | โ | โ | 32,952,100.20 | โ | 38.88Mn 21.4% |
| 97 | RDA/DRP/NWP/KURU/KURU/02R | Rehabilitation / Improvement and Structure Improvement of Mallawapitiya Rambodagโฆ | Can Construction and Consultancy (Pvt) Lโฆ | 208,660,417.21 | โ | โ | โ | โ | โ | โ | โ | โ | โ | โ | โ | โ |
| 98 | RDA/DRP/NWP/KURU/KURU/03R | Rehabilitation / Improvement of Thalgodapitiya Yatawaththa Road (B409) (9+100 -โฆ | Jayawansa Construction (Pvt) Ltd | 129,109,243.85 | โ | โ | โ | โ | โ | โ | โ | โ | โ | โ | โ | โ |
| 99 | RDA/DRP/NWP/KURU/KURU/04 | Rehabilitation / Improvement of Muththettugala Hiripitiya Road (B300) (10+880 โฆ | TMC Construction (Pvt) Ltd | 97,503,423.17 | 16,053,895.12 | 18,943,596.24 | โ | โ | 11,350,228.21 | 13,393,269.29 | โ | โ | 27,404,123.33 | โ | 32.34Mn Watch33.2% | 32.34Mn 33.2% |
| 100 | RDA/DRP/NWP/KURU/MAHO/05 | Rehabilitation / Improvement of Galgamuwa - Nikawewa Road (B126) (6+000-20+000),โฆ | St. Anthony's Construction | 151,515,024.36 | 27,548,186.25 | 32,506,859.78 | โ | โ | โ | โ | โ | โ | 27,548,186.25 | โ | 32.51Mn Watch21.5% | 32.51Mn 21.5% |
| Total | 34,005,299,486.17 | 2,787,819,645.29 | 3,289,427,166.63 | 113,218,826.01 | 133,598,214.69 | 1,049,943,508.60 | 1,238,847,524.51 | 63,842,351.18 | 73,647,937.02 | 3,837,763,153.89 | 177,061,177.19 | 4,528.27Mn 13.3% | 4,735.52Mn 13.9% | |||