DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 5 awarded projects

2026-11-04
17:17:26Live2026-11-04
0 / 5Advance Pendingpending advance projects / total projects
0 / 5IPC Pendingpending IPC projects / total projects
0 / 5Advance Paidadvance paid projects / total projects
1 / 5IPCs PaidIPC paid projects / total projects
343.9 Mn

343.85 Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

15.2 Mn

15.20 Mn

IPCs Paid (excl. VAT)

15.2 Mn

15.20 Mn

Total Paid (excl. VAT)

17.9 Mn

17.94 Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

17.9 Mn

17.94 Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

4.4%

4.4%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

85.2%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Trincomalee · District

171Projects34,005.3Contract Mn
Reset
Trincomalee 5 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency5343.917.95% of contract————1115.279.1%4.4%
DC - Roads00.0——————————
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
Trincomalee5343.917.95% of contract0.0000.01115.279.1%4.4%
Emergency5 projects343.9Mn
5% paid17.9 Mn
Pending—
Planned Fin79.1%
Actual Fin4.4%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid1 proj · 15.2 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Trincomalee5 projects343.9Mn
5% paid17.9 Mn
Pending0.0Mn
Planned Fin79.1%
Actual Fin4.4%

Avg Physical Progress per Province · Trincomalee

Graphs reflect current view:5 awarded · Trincomalee
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 3 projects (filtered from 171)

1–3/3 (filtered from 171)

Filter financial register

3 matching projects1 active

ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
1RDA/DRP/SAB/RAT/PEL/19
Rehabilitation / Improvement and Retaining wall Construction of (Galle - Deniya…
Solinro Builders
95,082,996.5816,436,817.5619,395,444.72——38,373,715.8845,280,984.74——54,810,533.44—
64.68Mn
68%
On Track
64.68Mn
68%
2RDA/DRP/NCP/POL/POL/08
Rehabilitation / Improvement and Reconstruction of 31/1 Culvert, Construction Of…
Sawsiri Construction
17,459,311.37————9,866,233.2111,642,155.19——9,866,233.21—
11.64Mn
66.7%
On Track
11.64Mn
66.7%
3RDA/DRP/SP/GAL/GAL/02
Rehabilitation of Gabbion Walls along Galle - Deniyaya - Madampe Road (from7+700…
Ceylon Construction Industry Development…
8,991,852.34————————————
Total121,534,160.2916,436,817.5619,395,444.72——48,239,949.0956,923,139.93——64,676,766.65—
76.32Mn
62.8%
76.32Mn
62.8%