DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 6 awarded projects

2026-11-04
15:22:15Live2026-11-04
1 / 6Advance Pendingpending advance projects / total projects
0 / 6IPC Pendingpending IPC projects / total projects
2 / 6Advance Paidadvance paid projects / total projects
1 / 6IPCs PaidIPC paid projects / total projects
43.6 Mn

43.60 Mn

Advance Paid (excl. VAT)

11.4 Mn

11.35 Mn

IPCs Paid (excl. VAT)

55.0 Mn

54.95 Mn

Total Paid (excl. VAT)

64.8 Mn

64.84 Mn

Total Paid (incl. VAT)

38.9 Mn

38.88 Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

103.7 Mn

103.73 Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

10.4%

10.4%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

66.7%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Emergency · Kurunegala · District

144Projects24,785.9Contract Mn
Reset
Kurunegala 6 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency6843.364.88% of contract38.93243.63111.465.1%6.5%
DC - Roads00.0——————————
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
Kurunegala6843.364.88% of contract38.93243.63111.465.1%6.5%
Emergency6 projects843.3Mn
8% paid64.8 Mn
Pending38.9Mn
Planned Fin65.1%
Actual Fin6.5%
Advance & IPC
Advance paid2 proj · 43.6 Mn
IPC paid1 proj · 11.4 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Kurunegala6 projects843.3Mn
8% paid64.8 Mn
Pending38.9Mn
Planned Fin65.1%
Actual Fin6.5%

Avg Physical Progress per Province · Emergency · Kurunegala

Graphs reflect current view:6 awarded · Emergency · Kurunegala
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 3 projects (filtered from 171)

1–3/3 (filtered from 171)

Filter financial register

3 matching projects1 active

ActiveProgress 100–100%
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
1RDA/DRP/SAB/RAT/PEL/19
Rehabilitation / Improvement and Retaining wall Construction of (Galle - Deniya…
Solinro Builders
95,082,996.5816,436,817.5619,395,444.72——38,373,715.8845,280,984.74——54,810,533.44—
64.68Mn
68%
On Track
64.68Mn
68%
2RDA/DRP/NCP/POL/POL/08
Rehabilitation / Improvement and Reconstruction of 31/1 Culvert, Construction Of…
Sawsiri Construction
17,459,311.37————9,866,233.2111,642,155.19——9,866,233.21—
11.64Mn
66.7%
On Track
11.64Mn
66.7%
3RDA/DRP/SP/GAL/GAL/02
Rehabilitation of Gabbion Walls along Galle - Deniyaya - Madampe Road (from7+700…
Ceylon Construction Industry Development…
8,991,852.34————————————
Total121,534,160.2916,436,817.5619,395,444.72——48,239,949.0956,923,139.93——64,676,766.65—
76.32Mn
62.8%
76.32Mn
62.8%