60.3% awarded

0

Awarded

63 total projects 63 roads in portfolio

1,296.2M

1,296.2 Mn

Contract Value

Spent 42.2% Remaining 57.8%
Avg
62.8%

16

works in progress

15 completed

Avg Progress

546.7M

546.7 Mn

Total Expenditure (incl. VAT)

42.2% of contract incl. VAT
81.6%

0

On Progress

31 / 38 awarded

0%

0

Delay

0 / 38 awarded

0%

0

Critical Delay

0 / 38 awarded

Portfolio Breakdown · North Central Province · Anuradhapura · District

58Awarded84Total
Anuradhapura 38 awarded of 63 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn125742%989.6209.2—54.626% of contract0.0%70.0%
Tender Below 50Mn34221265%1,154.3634.1—148.623% of contract0.0%41.7%
DL Stage 01330100%109.0109.058.2101.593% of contract66.7%100.0%
DL Stage 02330100%84.684.6—38.846% of contract0.0%100.0%
DL Stage 03220100%99.799.7—77.578% of contract0.0%100.0%
DL Stage 04330100%159.6159.6—125.779% of contract0.0%100.0%
Not Specified6060%0.00.0————
Anuradhapura63382560%2,596.81,296.258.2546.742% of contract5.3%62.3%

Avg Physical Progress per EE Division · North Central Province · Anuradhapura

At-Risk Projects · North Central Province · Anuradhapura

16
Portfolio Timeline· 29 scheduled projects · North Central Province · Anuradhapura Toggle
Portfolio · Awarded Works

Awarded Projects

15 projects

15/15 (filtered)

Filter awarded works

15 matching projects1 active

ActiveCompleted
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/20/25/05/NCP/ANPRR/RDA/20/25/05
Meda oyamaduwa handiye sita ehetuwawa dakwa margaya
100%
37,593,399.5556,374,105.66Awarded
2RR/RDA/20/25/10/NCP/ANPRR/RDA/20/25/10
Manewe sita machchiyagama dakwa margaya
100%
31,702,147.5439,026,908.38Awarded
3RR/RDA/20/25/12/NCP/ANPRR/RDA/20/25/12
Thalakolawewa carpert margaye awasanaye sita kudagama haraha dakunu ela iuwra margaya
100%
37,091,276.8049,135,056.85Awarded
4RR/RDA/20/25/13/NCP/ANPRR/RDA/20/25/13
Maradankadawala Habarana pare kaudawa handiyen patangena rambewa gammanaya dakwa margaya
100%
21,609,366.3526,367,721.95Awarded
5RR/RDA/20/25/14/NCP/ANPRR/RDA/20/25/14
Kukulewa pansala asalin arambavee samadhigama haraha seeppukulama rambewa maragaya dakwa divena pare pasala asala sita margaya
100%
29,296,077.0044,635,822.37Awarded
6RR/RDA/20/25/02—
Anuradhapura - Kurunegala pradana pare paththara kade handiyen aramba vee kodigala dakwa diwena margaya
100%
50,844,733.3550,844,733.35Awarded
7RR/RDA/20/25/07—
Road from A9 main road to Karapikkada Carpet Road (0+290 - 0+960)
100%
21,229,780.6321,229,780.63Awarded
8RR/RDA/20/25/15—
Dikediyaya mahaweli pradhana ele sita galewela pradhana margaya
100%
36,922,235.4036,922,235.40Awarded
9RR/RDA/20/25/21—
Pawithrapura Road
100%
32,078,244.1032,078,244.10Awarded
10RR/RDA/20/25/08—
Jaya mawatha sita Kaththaragama pansala dakwa margaya
100%
15,557,589.2615,557,589.26Awarded
11RR/RDA/20/25/09—
Padavi para Rambukepuwewa mansandiye sita Elapath wewa margaya dakwa margaya
100%
36,917,003.9436,917,003.94Awarded
12RR/RDA/20/25/17—
Galwaduwawa Junction to Yaya 02 road of Thambuththegama Eppawala Road
100%
64,398,698.7764,398,698.77Awarded
13RR/RDA/20/25/24—
Konketiyawa School to Mayilankulama Vilage road
100%
35,296,893.9635,296,893.96Awarded
14RR/RDA/20/25/19—
Thalawa Tsunami junction to Indigaspathana road of Padeniya Anuradhapura Road
100%
64,760,087.2264,760,087.22Awarded
15RR/RDA/20/25/23—
Megichchawa Junction to Temple Road (Kulumeewakada Junction)
100%
37,500,731.4737,500,731.47Awarded