DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 9 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:9 awarded · Central Province · EE: Gampola

Portfolio Breakdown · Central Province · EE: Gampola · EE Office

80Awarded97Total
Gampola 9 awarded of 10 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn220100%122.0102.0100.911.411% of contract99.0%27.5%
Tender Below 50Mn65183%217.1120.077.766.756% of contract80.0%80.0%
DL Stage 01110100%29.029.029.020.972% of contract100.0%100.0%
DL Stage 02110100%21.321.321.313.764% of contract100.0%100.0%
DL Stage 030000%0.00.0————
DL Stage 040000%0.00.0————
Not Specified0000%0.00.0————
Gampola109190%389.5272.3228.9112.741% of contract88.7%72.8%

Avg Physical Progress per EE Division · Central Province · EE: Gampola

Portfolio Timeline· 9 scheduled projects · Central Province · EE: Gampola Toggle
Portfolio · Awarded Works

Awarded Projects

4 projects

4/4 (filtered)

Filter awarded works

4 matching projects1 active

ActiveDelayed only
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/04/25/19/CP/KYRR/RDA/04/25/19
Mulgama viduhala Asala sita lewalan dakwa
35%
25,917,512.5046,131,296.30Awarded
2RR/RDA/04/25/21/CP/KYRR/RDA/04/25/21
Galaha group sita finas kotasa Pahalagama-Ihalagama haraha nawa rohala dakwa Margaya
80%
22,711,029.0040,719,533.36Awarded
3RR/RDA/04/25/31(1)/CP/KYRR/RDA/04/25/31(1)
Paththunupitiya School road to Gampola Road through Pallegama Anguruwala
30%
50,476,865.2865,989,182.36Awarded
4RR/RDA/04/25/41/CP/KYRR/RDA/04/25/41
Karyala handiya pahala margya concrete kirima
85%
22,047,564.0039,022,781.94Awarded
Showing 1–4 of 4
Per page:
Source: DRRRP • 10 projects • Data updated 2026-11-02 10:30 • 19:57:49