DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 12 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:12 awarded · Mullaitivu

Portfolio Breakdown · Mullaitivu · District

579Awarded739Total
Mullaitivu 12 awarded of 22 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn127558%1,550.7843.0732.6260.131% of contract85.7%47.1%
Tender Below 50Mn3030%130.40.0————
DL Stage 01110100%46.446.4—28.862% of contract0.0%100.0%
DL Stage 02110100%110.8110.8110.891.783% of contract100.0%100.0%
DL Stage 03110100%63.963.963.943.067% of contract100.0%100.0%
DL Stage 04110100%26.426.4—15.960% of contract0.0%100.0%
PIU110100%586.7659.1——0.0%0.0%
Not Specified2020%0.00.0————
Mullaitivu22121055%2,515.31,749.7907.3439.525% of contract66.7%60.8%

Avg Physical Progress per EE Division · Mullaitivu

Portfolio Timeline· 10 scheduled projects · Mullaitivu Toggle
Portfolio · Awarded Works

Awarded Projects

4 projects

4/4 (filtered)

Filter awarded works

4 matching projects1 active

ActiveProgress 100–100%
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/13/25/09—
Aninchiyankulam 2nd Lane MUTE095
100%
46,445,947.7746,445,947.77Awarded
2RR/RDA/13/25/04—
Suthanthirapuram Main Road Package 1
100%
110,821,121.40110,821,121.40Awarded
3RR/RDA/13/25/05—
Suthanthirapuram Main Road Package 2
100%
63,852,534.3763,852,534.37Awarded
4RR/RDA/13/25/02—
Kokkilai Estuary fishing village Road
100%
26,445,698.0826,445,698.08Awarded
Showing 1–4 of 4
Per page:
Source: DRRRP • 22 projects • Data updated 2026-11-02 10:30 • 15:19:23