DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 11 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-02 10:30Live
Graphs reflect current view:11 awarded · Kalutara · EE: Kalutara

Portfolio Breakdown · Kalutara · EE: Kalutara · EE Office

20Awarded21Total
Kalutara 11 awarded of 12 Open filtered view
Implementation MethodTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Tender Above 50Mn1010%168.00.0————
Tender Below 50Mn770100%115.689.758.916.318% of contract57.1%77.5%
DL Stage 01110100%25.725.725.725.298% of contract100.0%100.0%
DL Stage 02110100%14.714.714.711.478% of contract100.0%100.0%
DL Stage 03110100%14.814.814.88.356% of contract100.0%100.0%
DL Stage 04110100%12.512.512.56.149% of contract100.0%100.0%
Kalutara1211192%351.4157.4126.667.443% of contract72.7%85.7%

Avg Physical Progress per EE Division · Kalutara · EE: Kalutara

Portfolio Timeline· 11 scheduled projects · Kalutara · EE: Kalutara Toggle
Portfolio · Awarded Works

Awarded Projects

6 projects

6/6 (filtered)

Filter awarded works

6 matching projects1 active

ActiveProgress 100–100%
#Contract No. Package No. Contract Name Progress LOA Amount Estimate Amount Status
1RR/RDA/03/25/02/WP/KTRRR/RDA/03/25/02
Concreting of the first side road on the left side of Rasik Road
100%
7,705,537.2011,126,896.75Awarded
2RR/RDA/03/25/03/WP/KTRRR/RDA/03/25/03
Carpeting of Uswatta Lane
100%
6,059,612.507,444,801.70Awarded
3RR/RDA/03/25/01—
Asphalting Samagipura Road (LECO office to Maha ela)
100%
25,713,214.4025,713,214.40Awarded
4RR/RDA/03/25/07—
Carpeting of Shekmadara Road
100%
14,674,228.6514,674,228.65Awarded
5RR/RDA/03/25/11—
Jilani road in Darga Town
100%
14,759,196.1314,759,196.13Awarded
6RR/RDA/03/25/20—
Development of Gemunu Mawatha by laying 500 meters of carpet
100%
12,547,527.7812,547,527.78Awarded
Showing 1–6 of 6
Per page:
Source: DRRRP • 12 projects • Data updated 2026-11-02 10:30 • 14:34:56