DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 55 awarded projects

2026-11-05
01:42:07Live2026-11-05
0 / 55Advance Pendingpending advance projects / total projects
0 / 55IPC Pendingpending IPC projects / total projects
0 / 55Advance Paidadvance paid projects / total projects
0 / 55IPCs PaidIPC paid projects / total projects
2,249.3 Mn

2,249.31 Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

17.1%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Western Province · Province

579Projects23,829.3Contract Mn
Western Province 55 projects Open filtered view
CategoryImplementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
TenderTender Above 50Mn4207.010.45% of contract196.5——————0.0%0.0%
Tender Below 50Mn26391.794.824% of contract296.9——————30.8%0.0%
PIU1659.1—659.1——————0.0%0.0%
Tender Total311,257.7105.28% of contract1,152.5000.0000.025.8%0.0%
Direct LabourDL Stage 018211.8170.580% of contract41.4——————100.0%0.0%
DL Stage 02334.719.657% of contract15.0——————100.0%0.0%
DL Stage 03473.541.456% of contract32.1——————50.0%0.0%
DL Stage 049671.618.73% of contract653.0——————11.1%0.0%
Direct Labour Total24991.6250.125% of contract741.5000.0000.058.3%0.0%
—Western Province552,249.3355.416% of contract1,894.0000.0000.040.0%0.0%
Tender Above 50Mn4 projectsTender207.0Mn
5% paid10.4 Mn
Pending196.5Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn26 projectsTender391.7Mn
24% paid94.8 Mn
Pending296.9Mn
Planned Fin30.8%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU1 projectTender659.1Mn
0% paid0.0 Mn
Pending659.1Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 018 projectsDirect Labour211.8Mn
80% paid170.5 Mn
Pending41.4Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 023 projectsDirect Labour34.7Mn
57% paid19.6 Mn
Pending15.0Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 034 projectsDirect Labour73.5Mn
56% paid41.4 Mn
Pending32.1Mn
Planned Fin50.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 049 projectsDirect Labour671.6Mn
3% paid18.7 Mn
Pending653.0Mn
Planned Fin11.1%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Western Province55 projects2,249.3Mn
16% paid355.4 Mn
Pending1,894.0Mn
Planned Fin40.0%
Actual Fin0.0%

Avg Physical Progress per Province · Western Province

Graphs reflect current view:55 awarded · Western Province
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

91–100/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
91RR/RDA/17/25/02/EP/TRN
Kathirkamathambi Road
Fareed
28,809,738.00————————————
92RR/RDA/17/25/03/EP/TRN
Hospital Road
Pragash Construction
18,557,253.77————————————
93RR/RDA/17/25/05/EP/TRN
Improvement to Jeyanthiwewa to Track 12 Main Road
Nirupama Construction
103,260,000.00————————————
94RR/RDA/17/25/06/EP/TRN
Malporuwa to Thalgaswewa
Jeezan Trading and Transport
109,630,000.00————————————
95RR/RDA/17/25/07/EP/TRN
Kanthamalawa Main Road
SSK Construction
9,161,570.00————————————
96RR/RDA/17/25/09/EP/TRN
School-Galmetiyawa Main Internal Road
Zaka Engineering Consultancy
53,122,107.50————————————
97RR/RDA/17/25/10/EP/TRN
From Medagama temple to Peramaduwa
Soyuru Sampath Construction & Suppliers
24,197,635.00————————————
98RR/RDA/17/25/11/EP/TRN
Development of Road from near the Fair
MS Construction
25,280,343.60————————————
99RR/RDA/17/25/12/EP/TRN
Improvement of RDS Road
MTA Construction
30,166,053.00————————————
100RR/RDA/17/25/13/EP/TRN
Concreting from School junction to Boovidya Office
Hana Construction (Pvt) Ltd.
38,264,100.00————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 91–100 of 579 projects · page 10/58