DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 0 awarded projects

2026-11-05
04:23:31Live2026-11-05
0 / 0Advance Pendingpending advance projects / total projects
0 / 0IPC Pendingpending IPC projects / total projects
0 / 0Advance Paidadvance paid projects / total projects
0 / 0IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Total Contract

0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

0%

0%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

0%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Uva Province · Trincomalee · District

579Projects23,829.3Contract Mn
Trincomalee 31 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn4304.746.715% of contract258.0——————95.4%0.0%
Tender Below 50Mn24521.5195.738% of contract325.8——————0.0%0.0%
DL Stage 01132.230.194% of contract2.1——————100.0%0.0%
DL Stage 02115.415.6101% of contract-0.2——————100.0%0.0%
DL Stage 0300.0——————————
DL Stage 04143.228.967% of contract14.3——————100.0%0.0%
PIU00.0——————————
Trincomalee31917.1317.035% of contract600.0000.0000.022.0%0.0%
Tender Above 50Mn4 projects304.7Mn
15% paid46.7 Mn
Pending258.0Mn
Planned Fin95.4%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn24 projects521.5Mn
38% paid195.7 Mn
Pending325.8Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project32.2Mn
94% paid30.1 Mn
Pending2.1Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project15.4Mn
101% paid15.6 Mn
Pending—
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 030 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 041 project43.2Mn
67% paid28.9 Mn
Pending14.3Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
PIU0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Trincomalee31 projects917.1Mn
35% paid317.0 Mn
Pending600.0Mn
Planned Fin22.0%
Actual Fin0.0%

Avg Physical Progress per Province · Uva Province · Trincomalee

No province data available

Awarded projects will appear here

Graphs reflect current view:0 awarded · Uva Province · Trincomalee
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

461–470/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
461RR/RDA/21/25/28
Development of the road Sathutugama nidahas Mawatha Balance Section from the hou…
—
29,829,563.55————————————
462RR/RDA/20/25/19
Thalawa Tsunami junction to Indigaspathana road of Padeniya Anuradhapura Road
—
64,760,087.22————————————
463RR/RDA/20/25/23
Megichchawa Junction to Temple Road (Kulumeewakada Junction)
—
37,500,731.47————————————
464RR/RDA/20/26/23
First phase of Priman Mawatha via the by-road behind Kumbichchankulama tank
—
57,387,404.38————————————
465RR/RDA/21/25/25
School Main Road (Old Jumma Mosque Road)
—
43,759,842.36————————————
466RR/RDA/21/25/17
Hingurakgoda Samupakara Road to Bubula
—
174,553,300.63————————————
467RR/RDA/21/25/46
Girithale janapadaya pasal mawatha starting Section
—
22,545,305.56————————————
468RR/RDA/18/25/12
Anura Mahaththayalage niwase sita Nalalida dakwa kadurugaha ela dakwa margaya (G…
—
23,242,484.20————————————
469RR/RDA/18/25/05
158 Digana Grama niladari wasame 3 patumaga (vawa dakwa) (Yapahuwa)
—
11,774,916.28————————————
470RR/RDA/18/25/23
Horagasagara Nawarathna handiye sita Ihala kadigamuwa handiya dakwa margaya (Bin…
—
61,588,475.92————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 461–470 of 579 projects · page 47/58