DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 8 awarded projects

2026-11-04
21:37:30Live2026-11-04
0 / 8Advance Pendingpending advance projects / total projects
0 / 8IPC Pendingpending IPC projects / total projects
0 / 8Advance Paidadvance paid projects / total projects
0 / 8IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Badulla · EE: Badulla · EE Office

18Projects380.7Contract Mn
Badulla 8 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn00.0——————————
Tender Below 50Mn699.875.576% of contract24.3——————0.0%0.0%
DL Stage 01112.210.586% of contract1.7——————100.0%0.0%
DL Stage 02113.213.9105% of contract-0.7——————0.0%0.0%
Badulla8125.299.980% of contract25.3000.0000.012.5%0.0%
Tender Above 50Mn0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn6 projects99.8Mn
76% paid75.5 Mn
Pending24.3Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project12.2Mn
86% paid10.5 Mn
Pending1.7Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project13.2Mn
105% paid13.9 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Badulla8 projects125.2Mn
80% paid99.9 Mn
Pending25.3Mn
Planned Fin12.5%
Actual Fin0.0%

Avg Physical Progress per Province · Badulla · EE: Badulla

Project-wise Financials · Badulla · EE: Badulla (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · Badulla · EE: Badulla (Mn · incl. VAT)

Scroll horizontally — 579 projects

Badulla Division · Badulla · EE: Badulla (Mn · incl. VAT)

Badulla District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:8 awarded · Badulla · EE: Badulla
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

41–50/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
41RR/RDA/05/25/20/CP/MTL
Harispattuwa margaya arambaka mansandiye sita Thusitha maranadara godanagilla da…
Ajith Construction
15,584,937.50————————————
42RR/RDA/05/25/22/CP/MTL
Sigirimulla sita Mailetthewa Aluthyaya dakwa margaya
Asiri Contractor and Designers
33,057,264.90————————————
43RR/RDA/05/25/24/CP/MTL
Pahala Hombawa palama dakwa Daduwagolla kanaththa langa sita
Ajith Construction
35,817,952.50————————————
44RR/RDA/05/25/26/CP/MTL
Pallepola saukya karyalaye sita ekamuthugama dakwa margaya
Jayaru Engineering (Pvt) Ltd
18,760,083.54————————————
45RR/RDA/05/25/27/CP/MTL
Welemulla sita Kandewaththa
Ajith Construction
23,207,525.00————————————
46RR/RDA/05/25/29/CP/MTL
Pitawala handiye sita pitawala desata
Lahiru Construction & Consultants (PVT) …
37,136,372.90————————————
47RR/RDA/05/25/30/CP/MTL
Ganadewi pilimaya asala Kulathunga mahathage welanda sala dakwa
Lahiru Construction & Consultants (PVT) …
59,540,000.00————————————
48RR/RDA/06/25/32/CP/NE
Nanuoya Glaso pahala kotasa Margaya
wiscon (pvt) ltd
38,841,280.50————————————
49RR/RDA/06/25/34/CP/NE
Udupussellawa margaye Amasta handiye sita Ambagasdowa dakwa Margaya
NAGMA ENGINEERING (PVT) LTD
54,639,783.83————————————
50RR/RDA/06/25/37/CP/NE
Gewal wissa handiye sita Bogalkanda dakwa Margaye asiru sthan
Ajith Construction
28,282,100.00————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 41–50 of 579 projects · page 5/58