DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 8 awarded projects

2026-11-05
19:37:24Live2026-11-05
0 / 8Advance Pendingpending advance projects / total projects
0 / 8IPC Pendingpending IPC projects / total projects
0 / 8Advance Paidadvance paid projects / total projects
0 / 8IPCs PaidIPC paid projects / total projects
0.0 Mn

— Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (excl. VAT)

0.0 Mn

— Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

0.0 Mn

— Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

Portfolio Breakdown — Financial (Exclusive Vat) · Badulla · EE: Badulla · EE Office

18Projects380.7Contract Mn
Badulla 8 projects Open filtered view
Implementation MethodProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Tender Above 50Mn00.0——————————
Tender Below 50Mn699.875.576% of contract24.3——————0.0%0.0%
DL Stage 01112.210.586% of contract1.7——————100.0%0.0%
DL Stage 02113.213.9105% of contract-0.7——————0.0%0.0%
Badulla8125.299.980% of contract25.3000.0000.012.5%0.0%
Tender Above 50Mn0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Tender Below 50Mn6 projects99.8Mn
76% paid75.5 Mn
Pending24.3Mn
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 011 project12.2Mn
86% paid10.5 Mn
Pending1.7Mn
Planned Fin100.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
DL Stage 021 project13.2Mn
105% paid13.9 Mn
Pending—
Planned Fin0.0%
Actual Fin0.0%
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Badulla8 projects125.2Mn
80% paid99.9 Mn
Pending25.3Mn
Planned Fin12.5%
Actual Fin0.0%

Avg Physical Progress per Province · Badulla · EE: Badulla

Project-wise Financials · Badulla · EE: Badulla (579 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · Badulla · EE: Badulla (Mn · incl. VAT)

Scroll horizontally — 579 projects

Badulla Division · Badulla · EE: Badulla (Mn · incl. VAT)

Badulla District Summary (Mn · incl. VAT)

District baseline - overall all methods (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:8 awarded · Badulla · EE: Badulla
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 579 projects

251–260/579
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
251RR/RDA/12/25/57/NP/VVN
Nikawewa Right to Sapumalthanna
Yansika Construction
11,848,115.95————————————
252RR/RDA/12/25/58/NP/VVN
Preschool Road
5N Group Construction
21,518,222.00————————————
253RR/RDA/12/25/59/NP/VVN
Kalyanipura 2nd lane
5N Group Construction
28,184,992.00————————————
254RR/RDA/12/25/60/NP/VVN
Salalinigama lane 12
Sintha Construction (Pvt) Ltd
23,397,220.00————————————
255RR/RDA/12/25/62/NP/VVN
Periyavilathikulam
Omega Construction (Pvt) Ltd
16,916,712.50————————————
256RR/RDA/12/25/63/NP/VVN
1st Cross Street Alakarai Road
North Construction
38,912,500.00————————————
257RR/RDA/12/25/64/NP/VVN
Nedunkulama
Arul Selvi Construction and Hardware
15,902,966.56————————————
258RR/RDA/13/25/01/NP/MUL
Akkaraiveli Paraiyanaru ( Vilaththiyad) Road Package 1
Sun Constructions (Pvt) Ltd.
145,000,000.00————————————
259RR/RDA/13/25/03/NP/MUL
Navatkadu Road
TMC Constructions
50,363,687.00————————————
260RR/RDA/13/25/06/NP/MUL
Pandaravanniyan Silaiyadi Road
Sun Constructions (Pvt) Ltd.
83,700,000.00————————————
Total23,829,266,055.01——————————
—Mn
0%
—Mn
0%
Showing 251–260 of 579 projects · page 26/58