Physical Progress

25 Jun 2026

Physical Progress

Manage physical progress for 1 awarded projects

RDA/DRP/CEN/MTL/MTL/32

Kandy Jaffna Road A 009 (17+710 - 46+450), Thalgodapitiya Yatawatta Dombawela ro…

Lahiru Construction and Consultants (Pvt) Ltd

Matale Matale Awarded
Current Progress
Overall 22%
Critical Issues
Mobilization 100%
Surveying 50%
Site Clearing 40%
Base Construction 0%
Asphalt 0%
Structure Construction 10%
Drainage Construction 50%
Edit Progress
View Project