Ditwah(CP) Dashboard

Project Monitoring Dashboard

Comprehensive overview of 2 infrastructure projects · Emergency Projects · Nalanda EE 06:54:35 Live

Central Province 2 total
100% awarded

0

Awarded

62.2M

62.2 Mn

Contract Value

Avg

0

Avg Progress

11.8M

11.8 Mn

Total Expenditure

Project-wise Progress — Nalanda EE (2 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear
Project-wise Physical Progress: Actual vs Planned (%) — Nalanda EE
Average Physical Progress by EE Division (Nalanda EE)
Average District-wise Physical Progress (Matale District)

Matale district — overall emergency projects (now filtered to Nalanda EE)

Overall Physical Progress
Average
65%Physical

0

Completed

2

In Progress

Overall Financial Progress
Utilized
18.9%Financial

62.2 Mn

Contract Value

11.8 Mn

Total Paid

Awarded Projects

Awarded Projects

2 projects · Emergency Projects

XLSX Showing 2 of 2
Contract No. Road Name Progress Amount Status
RDA/DRP/CEN/MTL/NAL/49 Naula- Elahera-Pallegama-Hettipola Road (B-312) (8+200-61+240)
65%
44,706,119.13 Awarded
RDA/DRP/CEN/MTL/NAL/51 Bowathenna Access Road (B-064) (0+000-2+410)
65%
17,458,592.78 Awarded
Source: ditwah_projects • 2 projects • Updated 2026-09-07 06:54 • 06:54:35